Manual on PPP projects, management and execution
Summary
6 – KPIS................................................................................................................................................................................84 Annex 7 – Conflict resolution summary...........................................................................
6 – KPIS................................................................................................................................................................................84
Annex 7 – Conflict resolution summary.................................................................................................................................87
Annex 8 – Tools and templates.................................................................................................................................................88
Annex 9 – Mortgages on assets and rights of the financing entity............................................................................92
4
Manual on PPP projects, management and execution
PPP PROJECTS MANUAL
4
Manual on PPP projects, management and execution
5
Manual on PPP projects, management and execution
INTRODUCTION
I.
GLOSSARY
> Chapter 1: Introduction
TERM
DEFINITION
The state
The United Arab Emirates.
The government
The United Arab Emirates government.
The ministry
The ministry of finance.
The minister
The minister of state for financial affairs.
General budget committee
The cabinet committee that is responsible for proposing the general proce
dures of the federal financial policy, studying financial policies and legislation
and their impact on the economy to ensure the financial stability of the state,
and submitting recommendations thereon to the council of ministers.
Grievances committee
sector-specific plan identifying the objectives of PPP projects within the
sector, the list of PPP Projects within the sector, and the timeline for their
implementation.
Request for proposals (RFP)
A tender document that a concerned federal entity issues to bidders, re
questing their submission.
Request for qualifications
(RFQ)
A tender document issued to potential bidders to evaluate their capabilities
and/or qualifications in relation to bidding for a PPP project.
Sector PPP team
A team formed by key federal entities’ staff members in a particular
sector.
Statement of qualifications
(SOQ)
A statement submitted to the concerned federal entity in response to an RFQ
for a PPP project.
Tender
The procedures carried out by a governmental entity that includes requests
and approvals of proposals for a specific project.
Value for money (VfM)
Incremental value generated/ money that the government would save if a
project was implemented through a PPP as compared to traditional
procurement.
1. Minimum Project ROI is the lowest rate of return on investment that a project must achieve in order to be commercially viable from an investor’s
perspective.
7
Manual on PPP projects, management and execution
> Chapter 1: Introduction
II. PREFACE
III. AIMS OF THIS MANUAL
This manual clarifies governance and procedures
to follow when designing and implementing a PPP
project. It summarizes the guidelines and
processes that federal entities and potential
OF THIS MANUAL
This manual clarifies governance and procedures
to follow when designing and implementing a PPP
project. It summarizes the guidelines and
processes that federal entities and potential
private sector partners should follow when aiming
to engage in a PPP project. This ensures clarity
and consistency between stakeholders.
Public private partnerships (PPPs) can diversify
the mechanisms for developing strategic infra
structure projects and improve the quality of
services. At the same time, PPPs give the govern
ment authority to supervise and evaluate quality
and efficiency during the implementation of these
projects.
The government strives to benefit society, the
state, the private sector, and the local/national
economy through strategic PPP development
projects. It is also aware that implementing these
projects can be challenging and complicated.
The issuance of this manual is a first step in
successfully developing major strategic projects
and supporting the national economy. This
manual serves as an open invitation to the private
sector to make a positive contribution to the
state’s efforts.
A. In relation to the ministry
This manual:
— Provides clear guidelines on the ministry’s
involvement throughout the PPP process
and its interactions with other key
stakeholders.
The ministry prepared this manual to document
the general guidelines and procedures relating
to partnership contracts between federal entities
and the private sector. These guidelines and pro
the cabinet
resolution.
— The provisions apply to all processes
relating to PPP contracts outlined in this
manual.
— The relevant department in the federal
entity will follow the procedures in this
manual when planning or implementing a
project under a PPP.
— In the case of a conflict between
the provisions in this manual or the
implementation of the PPP contract and
any other applicable law, the provisions of
the federal law will prevail. The contract
may be completed only after obtaining a
formal exception or resolving the conflict.
C. In relation to the private
sector
This manual:
— Clarifies private sector partners’ rights
and liabilities under a PPP contract.
— Provides guidance on the bidding and
tendering process for potential private
sector partners.
— Should any aspect of the manual
be ambiguous or require further
interpretation, it is advisable to consult
the ministry for authoritative guidance.
— The internal audit regulatory units in each
federal entity and state audit institution
or equivalent will be responsible for
ensuring that federal entities apply the
guidelines and principles in this manual.
They will monitor any infringements
or breaches and recommend internal
controls and monitoring systems for the
implementation of PPP projects.
— Any PPP project started before the date
of release of this manual should follow
the previous manual. All new, planned,
amended, renewed, or extended PPP
projects evaluated or procured post the
Any PPP project started before the date
of release of this manual should follow
the previous manual. All new, planned,
amended, renewed, or extended PPP
projects evaluated or procured post the
date of the release of this manual should
follow this manual as per the law article
(32).
> Chapter 1: Introduction
9
Manual on PPP projects, management and execution
C. Updates
The ministry will be responsible for regu
larly reviewing, updating, and amending the
guidelines in this manual. Suggestions for
updates or amendments can also be made by
federal entities. If an amendment is approved,
the ministry will commit to:
— Consider additional modifications.
— Update the relevant procedures.
— Provide clear information to all federal
entities about the updates.
— Address any questions or inquiries about
amending or updating the manual.
D. Training
To ensure the effective implementation of
this manual, it is recommended that federal
entities provide training for employees,
either annually or when an updated version is
released, whichever comes first.
Training can be provided via workshops to
enhance understanding of the PPP project
process.
> Chapter 1: Introduction
10
Manual on PPP projects, management and execution
PPP OVERVIEW
I.
OVERVIEW OF PPP
PPPs involve the sharing of risks between
the public and private partners. Both parties
assume risks which are in line with their
ability and appetite.
PPPs often involve the private sector
partner providing financing for the project,
public and private partners. Both parties
assume risks which are in line with their
ability and appetite.
PPPs often involve the private sector
partner providing financing for the project,
in addition to design, construction, and
operation.
Financing
A
Risk sharing
B
Long-term commitment
C
Innovation
D
PPPs often involve the private sector in
bringing new ideas, technology, and best
practices to a project.
PPPs are typically long-term agreements,
often lasting several decades. However, the
duration can vary according to the risk-
return profile of the selected projects.
Performance-based approach
E
Focus on the end user
F
PPPs have a strong focus on the end
user, with the goal of providing improved
services or infrastructure to the public.
PPPs often follow performance-based
contracts, with payment tied to the
achievement of specific performance
targets.
A public-private partnership is a collaborative
arrangement between the public and private
sectors to develop infrastructure projects and
improve the quality of services being provided
to the public. In a PPP, the public sector partners
with a private sector partner to jointly plan,
finance, construct, and/or operate/maintain an
asset or service.
The private sector partner brings in their
expertise, resources, and capital to the project,
while the public sector partner provides
oversight and regulatory support. PPPs are
commonly used to deliver infrastructure and
public services. The structure of a PPP can vary,
These functions are
typically assigned during the feasibility study and
laid out in the contracting model. The following
are the private partner’s functions:
Design (D): Includes creating a detailed
project plan, outlining the project’s scope, and
identifying key project milestones.
Build (B): When PPPs are used for new
infrastructure assets, the private partner is
typically required to build the asset and install all
equipment.
Rehabilitate (R): When a PPP involves an
existing asset, the private partner may be
responsible for rehabilitating or expanding the
asset.
Finance (F): When a PPP includes building or
rehabilitating an asset, the private partner is
typically also required to finance all or part of
the capital and operational expenditures.
Maintain (M): Entails maintaining the
infrastructure to a specified standard throughout
the duration of the contract.
Own (O): The private partner owns an asset
throughout the duration of the contract.
Transfer (T): Involves transferring the asset or
the operations & maintenance of a particular
project.
Lease (L): In some cases, the private partner
leases assets to the public entity for the duration
of the contract.
Operate (Op): A private partner’s operating
responsibilities to a PPP can vary widely
depending on the nature of the underlying asset
and associated service. For example, a private
partner could be responsible for:
—
Operating an asset and providing a bulk
service to a government off taker; for
on the nature of the underlying asset
and associated service. For example, a private
partner could be responsible for:
—
Operating an asset and providing a bulk
service to a government off taker; for
example, a bulk water treatment plant.
—
Operating an asset and providing services
directly to users; for example, a water
distribution system.
—
Providing support services, with the
government agency retaining responsibility
for delivering the public service to users;
for example, a school building that includes
janitorial service.
A. Types of PPPs
There are many variations and types of PPP
agreements which depend on the nature of
the project.
For any project, an appropriate PPP model
can be identified and considered by
answering three questions:
11
Manual on PPP projects, management and execution
> Chapter 2: PPP Overview - PPP Types and Models
3. How is the private partner paid?
User pays PPP: The private partner provides a service to users and generates revenue by charging users for that service (according to the partnership contract).
Government pays PPP: The government is the sole source of revenue for the private partner. Government payments can depend on the asset or service meeting contractually defined performance standards.
Hybrid payments PPP: In certain cases, particularly when the revenues collected from end users are insufficient to cover the private partner costs and desired profits, a combination of the previously mentioned payment methods is utilized.
roles are defined in the nomenclature. |
| BOOT | | X | | X | | X | | X | X | [same merged description cell as BOT] |
| BOLT | | X | | X | | | X | X | X | [same merged description cell as BOT] |
| BOO | | X | | X | | X | | | X | [same merged description cell as BOT] |
| DBM | X | X | | | X | | | | | [merged description cell for DBM, DBOM, DBO] These models are defined by the private partner designing and developing the project, typically without private financing. Private partner roles are described in the nomenclature. |
| DBOM | X | X | | X | X | | | | | [same merged description cell as DBM] |
| DBO | X | X | | X | | | | | | [same merged description cell as DBM] |
| DBFOMT | X | X | | X | X | | | X | X | [merged description cell for DBFOMT, DBFMT] These models are defined by the private partner designing and developing the project, including private financing. Private partner roles are de-scribed in the nomenclature. |
| DBFMT | X | X | | | X | | | X | X | [same merged description cell as DBFOMT] |
| ROT | | | X | X | | | | X | X | [merged description cell for ROT, ROO] These models are defined by the rehabilitation of an existing asset. Private partner roles are de-scribed in the nomenclature. |
| ROO | | | X | X | | X | | | X | [same merged description cell as ROT] |
Note: “X” marks the private partner role.
Manual on PPP projects, management and execution 12
13
Manual on PPP projects, management and execution
> Chapter 2: PPP Overview - PPP Types and Models
|
Note: “X” marks the private partner role.
Manual on PPP projects, management and execution 12
13
Manual on PPP projects, management and execution
> Chapter 2: PPP Overview - PPP Types and Models
Table 2: Conditions of ownership of an asset under privatization versus a PPP
Under Privatization
Under a PPP
The private partner owns the asset.
Typically, the legal owner of the asset is the
government. Ownership can be transferred
to the private partner for the duration of the
contract only.
There is no strict contract, but authorizations
and conditions are regulated for the respective
market sector.
The contract details the rights and obligations of
each party.
The time to operate the asset is unlimited.
Time is limited by the contract.
Privatization does not involve strict alignment
of objectives as the government is usually
not involved in the output specification of the
privatized entity.
The government specifies, in detail, the quantity
and quality of the service it requires.
C. Exempted contracts
The guidelines outlined in this manual do not
apply to the following contracts and scenarios:
Outsourcing contracts: An outsourcing contract
is a legal agreement between an entity and an
external service provider (“outsourcer”) in which
the outsourcer agrees to perform certain tasks
or provide certain services to the government.
These tasks or services are typically ones the
government would otherwise perform itself but
chooses to outsource to save money, improve
certain tasks
or provide certain services to the government.
These tasks or services are typically ones the
government would otherwise perform itself but
chooses to outsource to save money, improve
efficiency, or focus on core competencies.
Outsourcing contracts can cover a wide
range of services, including manufacturing, IT
support, customer service, and research and
development. They can be long-term or short-
term agreements and often include specific
terms and conditions for performance, payment,
and dispute resolution — there is no risk sharing
for these types of contracts.
Partnership contracts concluded before the
entry into force of Law in 2023: Represents any
feasibility study initiated for a PPP project or any
ongoing contract that was issued before the law
and the manual came into force. The exemption
doesn’t apply to the renewal, amendment, or
extension of a project agreement as per article
(32) of the law.
Projects whose value is less than the defined
threshold: Represents any project valued below
AED 150 million, as stated in chapter 4 section 1
of this manual.
Procurement contracts related to national
security: Represents contract related to defence
equipment and technology, cybersecurity
solutions, intelligence and surveillance systems,
critical infrastructure, emergency services and
supplies, and research and development.
Federal entities, sectors, and projects that are
excluded by cabinet decision: Represents any
systems,
critical infrastructure, emergency services and
supplies, and research and development.
Federal entities, sectors, and projects that are
excluded by cabinet decision: Represents any
project or category of projects that have been
officially excluded by the cabinet.
Privatization: Refers to full ownership of assets
and services by the private partner. The following
table highlights the main differences between
PPP projects and privatization — there is full
transfer of risk in privatization.
14
Manual on PPP projects, management and execution
Differentiating between outsourcing,
privatization, and a PPP
PPP projects are the middle ground between privatization and
outsourcing. The following highlights each player’s level of
participation in different types of projects.
Contracts for performing
certain work (outsourcing)
Partnership between public
and private sector (PPP)
Privatization
Public sector
control
Mutual benefit and
partnership in risk and returns
Private sector
control
Public Sector
Private Sector
> Chapter 2: PPP Overview - PPP Types and Models
14
Manual on PPP projects, management and execution
15
Manual on PPP projects, management and execution
> Chapter 3: PPP Governance
PPP GOVERNANCE
I.
OVERVIEW
The governance structure in this manual covers
only federal and federal–local projects. It aligns
with federal law no. (12) of 2023, which regulates
partnerships between the federal public sector
and the private sector.
The state adopts a central governance model
federal–local projects. It aligns
with federal law no. (12) of 2023, which regulates
partnerships between the federal public sector
and the private sector.
The state adopts a central governance model
for its federal and federal–local projects. In
each project, the stakeholders are the cabinet,
the general budget committee, the ministry,
the PPP section working under the ministry, the
concerned federal entity and the project team.
II. GOVERNANCE STRUCTURE
A well-defined governance structure with clear
roles and responsibilities for stakeholders and
their interactions is essential for enhancing
transparency, promoting accountability, and
ensuring that private sector involvement
provides the maximum benefits to society.
The organization for economic cooperation
and development recommends following three
principles for the public governance of PPPs:
—
Establish a clear, predictable, and legitimate
institutional framework supported by
competent and well-resourced authorities.
—
Ground the selection of public private
partnerships in value for money.
—
Use the budgetary process transparently to
minimize fiscal risks and ensure the integrity
of the procurement process.
Cabinet
General Budget Committee
Project Team
Ministry of Finance
Concerned Federal Entity
Sector PPP team
Proposed
governance structure
PPP Section
> Chapter 3: PPP Governance
III. INSTITUTIONAL ROLES AND RESPONSIBILITIES
management and execution
A. Cabinet
The cabinet:
— Decides on the final approval or rejection of
the PPP plan.
— Decides on the final approval or rejection of
the feasibility study of PPP projects.
— Decides on the final approval or rejection of
the selected bidder(s).
— Grants additional incentives or exemptions to
concerned federal entities and private sector
players.
B. General budget committee
The general budget committee:
— Decides on the approval or rejection of the
PPP plan, including budget allocation if
required.
— Decides on the approval or rejection of the
feasibility study, only in case additional
budget is required.
— Decides on the approval or rejection of
selected bidder(s), only in case additional
budget is required.
C. Ministry
The ministry:
— Prepares, issues, and amends manuals and all
forms and documents related to PPP projects.
— Suggests updates to the legislation regulating
PPP projects in accordance with international
best practices.
— Works to provide the appropriate environment
to attract the private sector to participate in
PPP projects and overcome difficulties that
may hinder the success of PPP projects.
— Acts as an intermediary between the
concerned federal entity, general budget
committee and cabinet.
— Assists federal entities offering PPP projects
in accordance with the law, if necessary, and
encourages them to consider all projects for
PPP.
— Assigns a point of contact to give project
teams guidance, relevant tools and templates,
the tender documents and this manual.
—
Ensure the principles of transparency, fair
competition, and equal projects are applied
in accordance with the provisions of the law
and this manual.
F. Private sector
The private sector partners:
—
Submit expressions of interest (EoIs),
qualification documents, and bids.
—
Implement projects as per PPP contract
terms.
—
Propose potential PPP projects as unsolicited
proposals.
—
Raise capital for the projects as per the PPP
contract terms.
> Chapter 3: PPP Governance
20
Manual on PPP projects, management and execution
PPP PROJECT IMPLEMENTATION
AND EXECUTION MANUAL
21
Manual on PPP projects, management and execution
> Chapter 4: PPP Project Implementation and Execution
I.
IDENTIFICATION OF PROJECTS
Project
set-up
Yes
No
Reject
projects
1
2
3
5
7
4
6
Reject
projects
END
START
Review & share PPP plan
Review pre-feasibilities
and plan. Provide
comments if any, then share
with supreme budget
committee
Template/ checklist
Documents submission
Detailed in manual
Review prioritization &
share comments if any
List all services and
assets managed
by the entity
Assess projects
Assess all projects
identified and received
against the 5 defined crite-
ria to determine which are
implementable through
PPP
Prioritize projects
Prioritize projects based
on their impact and ease
of implementation
Develop pre-feasibility
& select projects
Develop pre-feasibility
studies and submit PPP
plan (incl. identification &
prioritization)
-Set up project team
their impact and ease
of implementation
Develop pre-feasibility
& select projects
Develop pre-feasibility
studies and submit PPP
plan (incl. identification &
prioritization)
-Set up project team
-Identify & consult
stakeholders
-Procure advisors
Approval
Approval
Concerned
Federal
Entity
Yes
No
Options analysis
(pre-feasibility)
Prioritization of
PPP projects
Identification of PPP
projects
MoF
(PPP
Section)
General
Budget
Committee
Cabinet
Every concerned federal entity must follow the
following process to implement PPP projects.
The decisions needed by the general budget
committee and the cabinet which are required
for the PPP plan, the feasibility study, and the
partner selection, can be taken during the pre-
scheduled budget committee meetings. Some
exceptions apply depending on the urgency of
the project and at the request of the concerned
federal entity.
In alignment with the process outlined below,
a federal entity is required to formulate a
strategic plan to utilize PPPs. Should an entity
already possess such a plan yet wishes to pursue
a new, unplanned opportunity, it may proceed
directly to step (5) of the process. At this
juncture, the entity’s focus would be to develop a
pre-feasibility study, as specified in section 2b of
this chapter, and subsequently secure approval
in accordance with the established procedure.
If there is no existing plan, and the concerned
federal entity intends to pursue an opportunity,
it must seek an exception from the ministry.
)
next
step
N/A
1.
2.
3.
4.
To identify projects for PPP, a
concerned federal entity must list and
assess all public facilities and assets
it manages, the public services it
provides, the activities it performs, and
its current and future capital projects.
The ministry and potential private
sector partners may also identify
PPP projects and suggest them to
the concerned federal entity. Any
project proposed by the ministry
must be added to the list. Potential
private sector partners may submit
an unsolicited proposal for a PPP (see
section b for more details).
The concerned federal entity assesses
all potential projects to determine
whether a function may be assigned to
the private sector through a PPP. The
assessment should be based on the
project assessment criteria.
Once the concerned federal entity
has selected projects that meet all five
project assessment criteria, it can move
to the project screening phase.
23
Manual on PPP projects, management and execution
B. Unsolicited proposals
What is an unsolicited proposal?
An unsolicited proposal refers to a feasibility
study on a potential PPP that is prepared by a
potential private sector partner and submitted
directly to a federal entity for consideration.
Who can propose or receive unsolicited
proposals?
The following conditions must be met before a
potential private sector partner may submit an
unsolicited proposal to a federal entity:
—
The decision to submit the proposal must
not be based on the request, participation,
must be met before a
potential private sector partner may submit an
unsolicited proposal to a federal entity:
—
The decision to submit the proposal must
not be based on the request, participation,
supervision, or guidance of a government
entity.
—
The party submitting the proposal must not
be a government entity or a government
employee, or an advisor appointed to
provide advisory services in relation to
infrastructure or public service projects.
Unsolicited proposal process:
—
The private sector drafts and submits the
project proposal, including initial feasibility
details, to the concerned federal entity or the
ministry. The level of details included should
be equal to the level of details of the pre-
feasibility study as described in this manual
(Chapter 4b), in addition to information
about the bidder, their experience, and their
qualifications.
—
The concerned federal entity should notify
the ministry as soon as they receive an
unsolicited proposal.
—
The concerned federal entity examines the
proposal to verify if the project is already
in the plan and if it has been submitted to
the appropriate entity. Based on this, the
concerned federal entity either approves the
proposal for further review, redirects it to the
appropriate entity or rejects it.
—
If the proposal is approved, it undergoes
a secondary review by the concerned
federal entity to check if the project aligns
with overall strategic goals and whether
it provides sufficient value for money and
the project is approved in the
secondary review, the private sector is
notified to develop a full feasibility study,
adhering to the guidelines specified in the
manual (as detailed in chapter 3).
—
The completed feasibility study is evaluated
by the concerned federal entity against
the assessment criteria established in the
manual. Depending on the evaluation, the
project team may receive comments for
adjustment or modification.
—
The ministry reviews the adjusted feasibility
study and comments if necessary and
checks it against the templates shared with
this manual.
—
The ministry then submits key inputs to the
cabinet for final decision.
—
If the study meets the required standards
and is approved by the cabinet, the project
moves to the tendering phase, otherwise it is
dropped.
Should a rejection occur at any stage of the
process, the concerned federal entity is
obligated to formally notify the prospective
private partner of this decision within ten
business days.
—
Partial reimbursement of study fees:
Recognizing the effort and resources
expended in preparing the proposal, the
proponent may be partially reimbursed
for the costs associated with conducting
feasibility studies and other preparatory
work. This reimbursement is not a full refund
but covers a portion of the expenses to
acknowledge the proponent’s investment in
identifying and outlining the PPP opportunity.
Tendering phase and proponent reward
If the project is approved, it will go through
Chapter 4: PPP Project Implementation and Execution
25
Manual on PPP projects, management and execution
To maintain fairness and transparency, the
concerned federal entity must notify the bidders
through the RFP that the opportunity originated
from an unsolicited proposal.
The project proponent is automatically qualified
to the RFP stage.
To protect confidential information, intellectual
property rights, trade secrets, and exclusive
rights in unsolicited PPP proposals, a Federal
Entity should have to follow two crucial
measures:
1.
The private party can request non-
disclosure agreements (NDAs): The
federal entity should require all internal
and external stakeholders involved in
the review and negotiation process to
sign NDAs before any proposal details
are shared. These agreements should be
legally vetted to ensure enforceability and
should clearly outline what constitutes
confidential information, the duration of
the confidentiality obligation, and the
consequences of breaches.
2. If the proposal contains potentially
patentable ideas or proprietary technology,
the private partner can request intellectual
property (IP) rights agreements: The federal
entity should work with legal experts to
draft IP agreements that clearly define the
ownership, use, and licensing of IP. These
agreements should address how IP rights
are handled during and after the evaluation
of the proposal, and in the case of project
award or rejection.
> Chapter 4: PPP Project Implementation and Execution
should address how IP rights
are handled during and after the evaluation
of the proposal, and in the case of project
award or rejection.
> Chapter 4: PPP Project Implementation and Execution
26
Manual on PPP projects, management and execution
II. PROJECT SCREENING
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Concerned
Federal
Entity
P02.
Feasibility
Study
Template
R01a.
Prioritization
checklist
1 month
The Ministry
2 weeks
N/A
A. Prioritization of PPP projects
Project
set-up
Yes
No
Reject
projects
1
2
3
5
7
4
6
Reject
projects
END
START
Review & share PPP plan
Review pre-feasibilities
and plan. Provide
comments if any, then share
with supreme budget
committee
Template/ checklist
Documents submission
Detailed in manual
Review prioritization &
share comments if any
List all services and
assets managed
by the entity
Assess projects
Assess all projects
identified and received
against the 5 defined crite-
ria to determine which are
implementable through
PPP
Prioritize projects
Prioritize projects based
on their impact and ease
of implementation
Develop pre-feasibility
& select projects
Develop pre-feasibility
studies and submit PPP
plan (incl. identification &
prioritization)
-Set up project team
-Identify & consult
stakeholders
-Procure advisors
Approval
Approval
Concerned
Federal
Entity
Yes
No
Options analysis
(pre-feasibility)
Prioritization of
PPP projects
Identification of PPP
projects
MoF
(PPP
Section)
General
Budget
Committee
advisors
Approval
Approval
Concerned
Federal
Entity
Yes
No
Options analysis
(pre-feasibility)
Prioritization of
PPP projects
Identification of PPP
projects
MoF
(PPP
Section)
General
Budget
Committee
Cabinet
> Chapter 4: PPP Project Implementation and Execution
)
27
Manual on PPP projects, management and execution
Table 4: Examples of factors considered in prioritizing projects
Factor
Metric
Unit
Assessment
method
Weight
Weight
rationale
Project value
CAPEX and
OPEX, for the 5
first years
Quantifiable
(AED)
High-level
estimation of
CAPEX and
OPEX
10%
Entity to
provide weight
rationale
Fiscal impact
Financial
impact on
government
budget
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
Social impact
Beneficiaries
reached
Quantifiable (#)
High-level
estimation
10%
Entity to
provide weight
rationale
STEPS TO FOLLOW
General assessment
factors
PROJECT IMPACT
1. Project Value
2. Fiscal Impact
3. Social impact
4. Alignment with sector’s objectives
5. Efficiency and quality improvement
EASE OF IMPLEMENTATION
1. Capacity and qualification of the
concerned federal entity’s human
resources
2. International success
3. Readiness of the regulatory
environment
4. Market capacity
5. Data availability
1.
2.
3.
4.
5.
The concerned federal entity must
use the general assessment factors
to score each potential project.
These factors are split into two main
categories: project impact and ease
of implementation. They can be either
qualitative or quantitative.
assessment factors
to score each potential project.
These factors are split into two main
categories: project impact and ease
of implementation. They can be either
qualitative or quantitative.
The concerned federal entity
may suggest up to five additional
assessment factors or sub-factors to
account for the varying characteristics
of different projects.
Once assessment factors for a potential
project are identified, the concerned
federal entity should assign weights to
each, depending on their importance.
After weighted scores are attributed to
the assessment factors, the concerned
federal entity will choose, according to
the prioritization output, the projects
that will qualify for the pre-feasibility
phase.
The ministry will then review the
prioritization exercise using the
checklist shared with this manual,
making sure it has been carried
properly.
> Chapter 4: PPP Project Implementation and Execution
28
Manual on PPP projects, management and execution
Table 5: Final assessment for prioritization exercise
Factor
Metric
Unit
Assessment
method
Weight
Weight
rationale
Efficiency and
quality improvement
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
Alignment with
sector’s objectives
N/A
Low
Medium High
Comparing
with
objectives
10%
Entity to
provide weight
rationale
Capacity and
qualification of the
concerned federal
entity’s human
resources
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
International
success
weight
rationale
Capacity and
qualification of the
concerned federal
entity’s human
resources
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
International
success
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
Readiness of
the regulatory
environment
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
Market capacity
Number of
potential
private partners
operating in the
region
Low
Medium High
High-level
research
10%
Entity to
provide weight
rationale
Data availability
N/A
Low
Medium High
High-level
estimation
10%
Entity to
provide weight
rationale
Project
Project
value
(AED)
Social
impact
score
Fiscal
impact
Score
Total score
Rank
First project
5 bn
High
High
100
#1
Second project
0.5 bn
Medium
Medium
67
#3
Third project
2 bn
High
Medium
80
#2
> Chapter 4: PPP Project Implementation and Execution
29
Manual on PPP projects, management and execution
1.
2.
3.
4.
5.
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Concerned
Federal
Entity
N/A
1 - 2 month
The Ministry
R01b. Pre-
Feasibility
Checklist
1 month
General
budget
committee
Cabinet
The concerned federal entity must
subsequently develop a pre-feasibility
study, according to the sections
described below, for each project that
passes the prioritization step.
The concerned federal entity shall
submit the PPP plan (including the
project identification, prioritization and
to the sections
described below, for each project that
passes the prioritization step.
The concerned federal entity shall
submit the PPP plan (including the
project identification, prioritization and
pre–feasibility study) to the ministry.
In addition to the PPP plan, the
concerned federal entity should
submit a high-level implementation
plan for selected projects and the
initial budget for developing the
feasibility studies.
The ministry evaluates each pre-
feasibility study based on the checklist
shared with the manual.
The ministry should share the plan with
the checklists and templates with the
general budget committee and then
cabinet for approval.
STEPS TO FOLLOW
B. Options analysis (pre-feasibility)
> Chapter 4: PPP Project Implementation and Execution
30
Manual on PPP projects, management and execution
TECHNICAL FEASIBILITY
The viability of a project must
be determined at an early stage.
Technical feasibility studies
enable the concerned federal
entity to justify the viability of
the project from technological,
environmental, social, and
market perspectives. Technical
feasibility studies should be
conducted for infrastructure
projects.
At this point, the concerned
federal entity does not need
to decide on the mode of
implementation for the project.
The technical feasibility should
include:
—
Preliminary findings on the
optimal technical option to
execute the project.
—
Costs associated with
each potential option and
service (maintenance) levels
technical feasibility should
include:
—
Preliminary findings on the
optimal technical option to
execute the project.
—
Costs associated with
each potential option and
service (maintenance) levels
expected for each option.
—
The impact of each option
on the environment and
society.
FINANCIAL FEASIBILITY
An initial financial analysis must
be conducted to determine
whether the project is financially
worthwhile and to develop
an initial view on which
implementation methodology
is best (the optimal PPP model).
The analysis includes:
—
The potential PPP models
through which the project
can be implemented (BOT,
ROT, etc.).
—
The public sector case
financials to assess the
costs on the government,
assuming the project is
completed by the public
entity.
—
The financials (income &
cashflow statements) for
all identified PPP models
and other possible non-PPP
implementation models
(typically outsourcing).
—
The value for money for each
model.
ANALYSIS OF THE CURRENT
SITUATION
Baseline analysis detailing
the current state of the asset
or service provided by the
government entity. This step is
mainly for brownfield projects.
The report should include high-
level details on the services or
assets currently being delivered
by the public sector, including:
—
The types of assets and
services delivered and the
beneficiaries.
—
The process for delivering
the services.
—
The performance of
the services and the
key operational gaps in
efficiency.
—
A breakdown of the capital
and
services delivered and the
beneficiaries.
—
The process for delivering
the services.
—
The performance of
the services and the
key operational gaps in
efficiency.
—
A breakdown of the capital
cost, project implementation
costs, operating costs and
revenues of the assets and
services.
PRE-FEASIBILITY STUDY SECTIONS:
MARKET ASSESSMENT
High level assessment of the
market which should include:
—
Market size: to determine
demand for the asset or
service linked to the project.
—
Comparable projects: to
identify similar local projects,
if any, or international
projects.
—
Initial potential players
identification: to identify
potential private partners
that might execute the
project.
30
Manual on PPP projects, management and execution
> Chapter 4: PPP Project Implementation and Execution
31
Manual on PPP projects, management and execution
LEGAL DUE DILIGENCE
An initial legal analysis must be conducted
to ensure the project is legally viable. This
analysis should identify:
—
Whether the project complies with PPP
and procurement laws.
—
Whether the project complies with land
ownership laws.
—
Any legislative amendments required if
the applicable laws are in conflict with
international practices.
—
The possibility of transferring or
terminating existing contracts related to
the project.
ECONOMIC ANALYSIS
A preliminary assessment to determine
the potential impacts of the project on the
economy. The analysis should take into
account both direct and indirect economic
to
the project.
ECONOMIC ANALYSIS
A preliminary assessment to determine
the potential impacts of the project on the
economy. The analysis should take into
account both direct and indirect economic
impacts as well as the project’s contribution
to Gross Domestic Product (GDP).
Direct economic impacts refer to the
changes in revenues and costs for the
government. Indirect economic impacts,
on the other hand, refer to the changes in
employment and consumer spending that
result from the project.
SOCIAL AND ENVIRONMENTAL ANALYSIS
An initial impact assessment to determine
the effects of a project on the environment
and on the society. This will help inform
decision-making about whether to proceed
with the project.
The analysis should consider potential
risks associated with these impacts. This
could include risks related to environmental
degradation, such as through pollution or
habitat destruction, and social impacts, such
as the risk of conflict with local communities,
limited access to usual roads, or any other
negative effects on citizens.
The assessment should also consider
potential opportunities, such as job creation
or social and environmental gains such
as improved access to clean water or the
restoration of natural habitats.
The analysis should be comprehensive
and include high level recommendations
for developing measures to mitigate any
negative impacts and maximise potential
benefits.
IMPLEMENTATION AND PROJECT
MANAGEMENT
A description of the project’s implementation
level recommendations
for developing measures to mitigate any
negative impacts and maximise potential
benefits.
IMPLEMENTATION AND PROJECT
MANAGEMENT
A description of the project’s implementation
plan, including a schedule, budget, and
resource requirements.
31
Manual on PPP projects, management and execution
> Chapter 4: PPP Project Implementation and Execution
32
Manual on PPP projects, management and execution
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Concerned
Federal
Entity
N/A
1 month
N/A
N/A
N/A
N/A
Overview
In between identifying the project and
conducting feasibility studies, it is useful to carry
out the following activities:
Stakeholder consultations
Interactions between stakeholders and the
parties involved in a PPP project play an
important role in its life cycle. The concerned
federal entity should identify the vital
stakeholder groups early in the process to enable
communication. This is essential for aiding their
understanding of the process; gaining social,
business, and political support for the project;
attracting potential investors; and reducing
project-related risks. It also assists with recording
their needs, concerns, worries, and interests.
Stakeholders are split into two categories:
Internal: These are public sector officers and
employees linked, directly or indirectly, to the
project cycle.
External: These are banks, investment funds,
government and multilateral funders, public
These are public sector officers and
employees linked, directly or indirectly, to the
project cycle.
External: These are banks, investment funds,
government and multilateral funders, public
service users, media, other government agencies
(that is, the municipality or government, or the
federal government), regulatory agencies and
legislators, and non-governmental organizations
(NGOs).
Lack of communication or poor communication
can feed false rumours that cause concerns that
can undermine a project’s success.
Therefore, it is important to develop an effective
communication plan. Typically, the plan will:
—
Identify all groups that should receive
communications.
—
Explain the main concepts to be
communicated, drawing on the basic
elements of the project, such as its
outcomes, the needs it will meet, and the
people it will serve.
—
Nominate the media used to reach the
identified groups.
—
Outline the main characteristics of the
communication pieces, preferably tailoring
them to each group identified.
C. Project set-up
> Chapter 4: PPP Project Implementation and Execution
33
Manual on PPP projects, management and execution
Hiring advisors
When setting up the project, it is crucial to
identify the capabilities needed. If the concerned
federal entity doesn’t have sufficient internal
capacity to perform the full appraisal, it should
hire advisors.
Advisors can aid in carrying out feasibility
studies, structuring the project, and managing
and analyses
throughout
Comments
Review and evaluate
Evaluate outcomes of the study
based on assessment criteria set in
the manual
Comments
No
Yes
No
Yes
Submit executive summary
and checklists
Submit an executive summary of the
feasibility as well as relevant checklists
(technical, financial & legal)
Review and comment
Assess the outcomes of studies,
provide comments to the project
team or pass to MoF
Project
Team
Concerned
Federal
Entity
MoF
(PPP
Section)
General
Budget
Committee
Cabinet
Approval
Yes
No
Drop
project
Go to next
step
Approval
Yes
No
Drop
project
Develop initial
analyses
Develop baseline & gap
analysis & market
assessment
Develop
technical, legal
& financial
feasibilities
Develop
contracting
model
Develop social,
economic &
environmental
analysis
-
Develop risk
analysis
Identify and rate risks
throughout project
life cycle
3
4
5
1
2
7
Develop
tendering plan
Detailed in manual
Template/ checklist
Documents submission
Feasibility
analyses
Final
analysis &
submission
Review &
approval
6
8
9
> Chapter 4: PPP Project Implementation and Execution
It is important to note that most of the studies are typically
conducted in parallel, with the total period for the development
of the feasibility study being around six months.
35
Manual on PPP projects, management and execution
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 weeks
Concerned
Federal Entity
The Ministry
R02.
Feasibility
Study
Checklist
At the end,
to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 weeks
Concerned
Federal Entity
The Ministry
R02.
Feasibility
Study
Checklist
At the end,
with all
studies
At the end,
with all
studies
A. Initial analysis
Overview and objectives
In order to gain a comprehensive understanding
of the market and the current situation
surrounding the project, it is essential to
conduct four key analyses. Including a current
state assessment, a market assessment, a
gap analysis, and an analysis of procurement
alternatives.
Current state assessment
This assessment is aimed at understanding the
current situation and conditions relating to the
project. It should include assessments of:
—
Infrastructure (if applicable): to evaluate
existing infrastructure, such as roads,
utilities, and transport networks impacted by
or required for the project.
—
Services delivered and beneficiaries (if
applicable): to identify the types of services
already being delivered by the public sector
and the beneficiaries of those services.
—
Current delivery model (if applicable): to
identify the current process for delivering
the services by the public sector.
—
Operational performance (if applicable):
to evaluate the performance of the services
provided by the public sector and identify
the major gaps in operational efficiency.
—
Financial performance: to break down the
services’ operating costs and revenues.
For brownfield PPP projects, the project team
public sector and identify
the major gaps in operational efficiency.
—
Financial performance: to break down the
services’ operating costs and revenues.
For brownfield PPP projects, the project team
must submit a detailed transition plan for existing
employees, assets, and processes.
Market sounding
The main objective of the exercise is to identify
all potential partners that possess the capability
and interest to carry out the project, and to
engage in meetings and discussions with them
to gain their insights and feedback on the
project.
—
The first step in the exercise is to compile an
exhaustive list of potential partners that may
be interested and capable of undertaking the
project.
—
The second step is to prepare a document
that outlines the project scope, including
high level technical and financial aspects,
as well as a potential risk sharing matrix and
a questionnaire to the potential partners,
which typically includes questions around:
• Potential partner overview: to understand
the potential partner’s experience,
footprint, and services provided.
• Potential partner interests: to gauge the
potential partner’s interest in potentially
pursuing the opportunity and identify key
preferences.
• Readiness assessment: to assess the
potential partner’s readiness and capacity
to engage in the required scope of work
for this opportunity.
• Technical overview: to understand the
potential partner’s technical expertise and
capabilities.
• Financial overview: To identify the
engage in the required scope of work
for this opportunity.
• Technical overview: to understand the
potential partner’s technical expertise and
capabilities.
• Financial overview: To identify the
potential partner’s payment preferences,
key cost buckets, and receive high-level
cost estimation.
• Concerns & key considerations: To
identify any potential obstacles and
critical factors for project success.
> Chapter 4: PPP Project Implementation and Execution
36
Manual on PPP projects, management and execution
—
The project team will then conduct meetings
with a select group of potential private
partners and through the questionnaire
the project team will gather essential
insights to confirm market appetite and
refine feasibility studies, thereby ensuring a
robust and competitive tendering process.
Market sounding is instrumental in any PPP
transaction, as it not only gauges interest,
capabilities, and financial benchmarks
but also sharpens the project scope and
identifies the optimal delivery model based
on stakeholder feedback. This step also
serves to cultivate preliminary interest
among potential investors and partners,
effectively functioning as an early marketing
initiative.
—
Finally, the project team should combine all
findings and key insights into one document.
Gap analysis
The results of the updated current state and
market assessments should be used to develop a
more accurate gap analysis.
This would fill potential gaps with precise
one that is
appropriate for the project and justify the
choice. Additionally, develop a risk allocation
matrix, outlining the expected distribution of
risks between the concerned federal entity
and the private sector. This matrix will ensure
the project team identifies the most suitable
and favourable PPP model for the project.
Options development
— List several options for completing the
project, including their respective costs.
All development options generated from
the technical feasibility study must rest on
the premise of delivering a quality service
that is cost-effective, energy-efficient,
environmentally friendly, and commercially
and economically viable.
B. Technical feasibility
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 - 4 months
Concerned
Federal Entity
The Ministry
At the end,
with all
studies
At the end,
with all
studies
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
37
Manual on PPP projects, management and execution
Technical design and engineering
— A high-level technical design must be
developed for the project. It must include
necessary engineering and architectural
plans, and an assessment of the availability
and suitability of materials, equipment, and
technologies to be used.
Operational analysis
— This must include an evaluation of the
operational requirements for the project,
including staffing and training needs,
maintenance, and potential risks and
to be used.
Operational analysis
— This must include an evaluation of the
operational requirements for the project,
including staffing and training needs,
maintenance, and potential risks and
challenges.
Estimation of project costs
— Estimate the total costs incurred to build,
renovate, and/or rehabilitate an asset or
provide a service, including operations and
maintenance costs.
Overview and objectives
The project team must examine legal issues
thoroughly in all aspects of the project. Detailed
due diligence will ensure compliance with all
legal requirements. The legal analysis aims to:
Inputs for bidding documents
— Provide inputs for the bidding documents
(mainly the RFQ and the RFP) such as
qualifications criteria, eligibility criteria, and
performance security.
Approvals and clearances
— Depending on the type of project, approvals
and clearances may be needed. These fall
under two categories:
1.
Administrative approvals: These will be at the
prerogative of the public entity.
2. Regulatory approvals and clearances from
boards, agencies, and/or authorities: The
public entity or the private partner can obtain
these, depending on the stage of the project
development process.
— Thoroughly assess the legal framework and
regulations for the PPP project.
— Help manage risks by identifying and
addressing risks and challenges in technical
and financial evaluations.
— Prevent major issues in project development
and implementation by considering
for general contract and
procurement guidelines.
— Foreign investment, property, and labour
legislation.
— Land use planning and environmental
legislation.
— Sector-specific legislation (For example,
penal and correctional facilities legislation
may prohibit private sector participation in
penal and correctional facility projects).
— Dispute resolution and intellectual property
law.
— Legislation regarding the transfer of
ownership, or control of public assets, or
delivery of public services to third parties.
— Legal treatment of project revenue sources.
2.
The second step involves evaluating the
legal readiness of the procuring authority.
This includes ensuring that the concerned
federal entity and other relevant
institutions have the legal authority to
initiate the project or grant approval.
3.
The third step is a comprehensive legal
analysis of key project issues. Large
infrastructure projects often have
unique and significant legal implications,
requiring assessment of:
— Financial aspects of the project.
— Commercial viability, including project
bankability.
— Use of land and existing assets.
— Potential ownership claims on the land.
— Rights of other users (e.g. state oil
company with pipes under the land or
a road under electricity transmission
wires).
— Employment and transfer of
employees.
— Tax and accounting issues in the
financial models.
> Chapter 4: PPP Project Implementation and Execution
39
Manual on PPP projects, management and execution
Employment and transfer of
employees.
— Tax and accounting issues in the
financial models.
> Chapter 4: PPP Project Implementation and Execution
39
Manual on PPP projects, management and execution
Table 6: Examples of legal matters that may need to be covered
Category
Example
Financials
— Due diligence of the selected type of public support or guarantees, where
needed.
— Approval process for public support and authorities involved.
— Legal restrictions and limitations for charging private sector end-users, if
applicable.
— Legal ability to develop collateral businesses (e.g. advertising, retail, and
leisure).
Land and
property
assets
— The type of rights that can be assigned to the private sector.
— The country-specific issues surrounding land availability (this can take the
form of right of way or clearance for transportation projects and/or site
ownership for facilities).
— Rules regarding ownership of assets.
— Responsibility for relocating people living in the right of way.
Employment
— Consequences for public sector employees if existing assets are to be
taken over by the private sector.
Taxation and
accountancy
— The regime applicable to the project.
— The regime applicable to imports (when significant equipment is included
in project CAPEX).
— Provision of tax exemptions and potential tax benefits for foreign direct
investment.
Environmental
— Environmental clearances that may be required by law for the particular
site or project type.
Provision of tax exemptions and potential tax benefits for foreign direct
investment.
Environmental
— Environmental clearances that may be required by law for the particular
site or project type.
— Environmental exemptions applicable to the site and/or project.
> Chapter 4: PPP Project Implementation and Execution
40
Manual on PPP projects, management and execution
Overview and objectives
The main aim of assessing the financial feasibility
of a PPP project is to ensure that implementation
using a PPP structure is financially viable for both
the government and the private sector partners.
This is accomplished by conducting a thorough
financial analysis, including forecasting the
project’s revenue and expenses, and evaluating
the risks and potential returns.
The analysis also considers factors such as the
availability of finance in the prevailing economic
and market capital. Ultimately, the goal is to
establish a financially viable partnership that
benefits the public and private sectors, while
also meeting the objectives of the project.
Financial case development
To fully assess a project’s feasibility, a financial
analysis should be conducted for four cases:
1.
The baseline case (brownfield projects):
This includes a comprehensive financial
analysis of the current and projected status
of the project if it was executed solely by the
government. This baseline analysis would
use current and historical financial inputs
and assume no improvement in quality or
increase in supply.
status
of the project if it was executed solely by the
government. This baseline analysis would
use current and historical financial inputs
and assume no improvement in quality or
increase in supply.
2.
The public sector case: This includes
assessing a project’s costs and revenues
if it were managed and executed by the
public sector while still achieving the same
level of coverage and/or public impact as
a PPP project. It serves as a benchmark
for evaluating the PPP financial case and
proposals.
D. Financial feasibility
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 - 4 months
Concerned
Federal Entity
The Ministry
At the end,
with all
studies
At the end,
with all
studies
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
41
Manual on PPP projects, management and execution
The PPP case:
3.
Government: Financial implications of
implementing the proposed project through
a PPP model. This analysis will consider the
costs and revenues the government will
assume and collect through the project. It
will be used to evaluate VfM.
4.
Private sector partner: This focuses on
financial analysis relating to the private
sector partner involved in the proposed
PPP project. It will provide a thorough
understanding of the financial implications
of the project for the private sector partner,
including costs and revenues. It will aid
the government entity in evaluating the
It will provide a thorough
understanding of the financial implications
of the project for the private sector partner,
including costs and revenues. It will aid
the government entity in evaluating the
project’s overall financial viability and
the partner’s capability to fulfil its related
financial obligations. It will also help ensure
that the PPP aligns with the partner’s
financial goals and objectives which are
usually a high Profit margin and Internal Rate
of Return (IRR).
After the project team has performed the four
financial analyses (refer to the following pages
for details), it can calculate the project’s VfM.
To do so, the project team:
— Determines the cash flows for the public
sector case for the duration of the contract.
— Determines the government’s cash flows, if
they were to execute the PPP, for the duration
of the contract.
— Discounts the cash flows using the weighted
average cost of capital (WACC) as the
discount rate. As shown in the formulas
below, the WACC for the private sector is
different than the one for the government.
The project team should also create sensitivity
analyses using as target variables the private
partner’s profit margin, IRR, and/or government’s
VfM.
The impact of risks, as described in section
G below, should also be considered when
computing cashflows and VFM.
VfM
NPV
(Public sector case)
NPV
(PPP–GOVT.)
WACC
(Private sector)
Cost of
equity
Private sector
Multiply by (1-tax rate) if any
%
Equity
Cost of
debt
%
Debt
WACC
(Government)
cashflows and VFM.
VfM
NPV
(Public sector case)
NPV
(PPP–GOVT.)
WACC
(Private sector)
Cost of
equity
Private sector
Multiply by (1-tax rate) if any
%
Equity
Cost of
debt
%
Debt
WACC
(Government)
Cost of
debt
Government
Since it’s not possible to determine the Govern-
ment’s capital structure, the Government WACC
should be considered = cost of raising debt
> Chapter 4: PPP Project Implementation and Execution
For all four cases
1
2
3
4
To forecast the inputs and assumptions for the
duration of the contract, growth assumptions on
must be made, mainly in relation to:
—
The country’s inflation rate: This is usually
used for forecasting the majority of costs.
—
The historical demand growth rate: This is
usually used for forecasting inputs correlated
with the outputs provided.
The project team can determine other types of
growth, if necessary.
For all four cases
1
2
3
4
Costs leveraged from inputs should cover all
costs to be incurred and include:
—
CAPEX (land, property, equipment, and
other capitalized costs).
—
OPEX (employee-related costs, utilities, rent,
consumables, maintenance, overheads, and
any other relevant operating costs).
—
Other costs (including taxes, depreciation,
and financing).
Importantly, in addition to the costs in the PPP
case, the government might have to make
payments to the private sector.
For the baseline case
For the public sector case
2
1
For the baseline case
1
For the public sector case
2
42
Manual on PPP projects, management and execution
possible.
Revenues should be deduced from inputs and
should include the total revenue from carrying
the project if it were to remain under government
management.
For the PPP case for the government
3
Revenues should be deduced from inputs and
assumptions and should include the total revenue
from carrying the project if it were to be trans
ferred to the private sector.
For the PPP case for the private sector
4
The private sector partner usually has two main
sources of revenue, depending on the PPP model:
—
Payments from the government to the
partner for developing the asset or carrying
the service.
—
Beneficiaries’ payments, which the partner
might receive directly from beneficiaries
depending on the type of project.
> Chapter 4: PPP Project Implementation and Execution
For all four cases
1
2
3
4
Build the following financial statements for
analysis:
—
The income statement: This details the
revenues and costs over the forecast period,
with net income deducted.
—
The cashflow statement: This includes any
type of cash adjustments used to determine
free cash flow, which is needed for the final
analysis (NPV calculations).
43
Manual on PPP projects, management and execution
Source of financing
The private sector thoroughly examines the
financing possibilities of PPP projects, which
involve a large amount of capital. In the case
of greenfield projects, where no cashflow will
be generated during the development stage,
the private sector is unlikely to solely fund the
which
involve a large amount of capital. In the case
of greenfield projects, where no cashflow will
be generated during the development stage,
the private sector is unlikely to solely fund the
project’s capital expenditure through equity.
There are conventional and non-conventional
ways to finance a PPP project, as shown in the
diagram below. Only conventional ways will be
explained in this manual.
CONVENTIONAL
EQUITY
DEBT
GRANT
NON-CONVENTIONAL
MEZZANINE DEBT
CAPITAL MARKETS
BORROWINGS
DERIVATIVE PRODUCTS
1
2
3
5. Develop financial statements
> Chapter 4: PPP Project Implementation and Execution
44
Manual on PPP projects, management and execution
1. EQUITY
The private partner manages the equity
arrangements for a public private partnership
project, which is typically provided by
consortium members of the private sector.
Other parties such as contractors, development
partners, or the public entity may also contribute
equity. In the event of project losses, equity
investors bear the first loss and lenders are only
affected if the equity investment is lost. Due to
the higher risk involved, equity investors require
a higher return on their investment compared to
debt providers.
The diagram shown illustrates the typical sources
of equity.
2. DEBT
In a public private partnership project, the
private partner is responsible for managing
the debt arrangements. This includes raising
funds from various sources such as banks,
development partners, government agencies,
partnership project, the
private partner is responsible for managing
the debt arrangements. This includes raising
funds from various sources such as banks,
development partners, government agencies,
and issuing bonds. The majority of the debt is
typically provided as “senior debt” by lenders.
As senior lenders do not have access to the
sponsors’ financial information, they need to
ensure that the project generates enough cash
flow to repay the debt. Additionally, they must
be given priority over other creditors in terms of
access to the project’s assets.
3. GRANT
The government may offer financial assistance
(or in some cases non-financial), in the form of
an upfront grant, to projects that are deemed to
be socially or economically beneficial but may
not be financially feasible without such support.
These grants are intended to help improve the
financial viability of the project by providing
funding for the initial capital expenditure. This
can help reduce the overall financial risk of the
project, making it more attractive to potential
investors and ultimately increasing the likelihood
of its successful completion. In addition, these
grants can also help to stimulate economic
growth and development by supporting projects
that have the potential to create jobs, improve
infrastructure, and promote innovation.
T YPICAL SOURCES OF EQUIT Y
T YPICAL SOURCES OF DEBT
Equity investors are interested in the project’s
IRR, Equity IRR & payback period
Owners /Stake-
holders contribution
and promote innovation.
T YPICAL SOURCES OF EQUIT Y
T YPICAL SOURCES OF DEBT
Equity investors are interested in the project’s
IRR, Equity IRR & payback period
Owners /Stake-
holders contribution
Development Banks
(i.e., EDB or World Bank)
Retained
profits
Issuance of
bonds
IPOs/
equity funds
Commercial
Banks
In kind
contribution
Bilateral funds
(AFESD)
> Chapter 4: PPP Project Implementation and Execution
45
Manual on PPP projects, management and execution
E. The contracting model
Overview and objectives
The contracting model sets the scope of the
project and details the obligations between the
private and public sector players. The project
team must develop it in conjunction with
consultants as it is the basis for the final contract
between the concerned federal entity and the
private partner. At a minimum, it should include
the sections described below. If necessary,
other sections can be added, depending on the
project’s needs.
1.
Scope of the project and the contract,
including contract duration, implementation,
and mechanism
The length and scope of the contract in a PPP
project can depend on the type of PPP being
used. It should have been chosen by the end
of the pre-feasibility stage. The contracting
model should clearly define the specific
objectives and deliverables that the private
partner is contracted to complete.
A PPP project can often take several years
to implement and go through multiple
tendering phases. The contracting model
the end,
with all
studies
At the end,
with all
studies
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
46
Manual on PPP projects, management and execution
3. Key performance indicators (KPIs) and
scoring to evaluate the private partner’s
performance
Set KPIs
Score the private
sector
Apply bonuses/
penalties
Setting up the KPIs involves:
1.
Identifying the strategic objectives that the project is trying to achieve.
2. Defining one or more KPIs for each objective.
3. Detailing each KPI (including reporting frequency, unit of measurement,
calculation methodology, source of data, weight of total score, and KPI
criticality).
Assign each KPI a score based on the company’s performance compared to
the expected performance (see the example of a service expected to take two
hours).
1.
After assigning a score to each KPI, add up the individual scores to find the
total score.
2. Depending on how this score compares to the target scores set in the con
tracting model, penalties or bonuses may be applied to the private sector
partner.
3. Individual KPIs with high criticality may also have penalties or bonuses
assigned to them.
Points
Poor
1
>3 hours
Good
3
2–3 hours
Excellent
5
<2 hours
Performance
KPIs deep dive
> Chapter 4: PPP Project Implementation and Execution
47
Manual on PPP projects, management and execution
4. Ownership of the project and its assets, and the
process for handover and change of ownership
or termination
An overview of the following rules should be
included in the contracting model:
—
Suspension: Provisions for the
suspension of the contract, such
as if one party is in breach of their
obligations or if there are unforeseen
circumstances that make it impossible
to continue with the project.
—
Modification: Provisions for the
modification of the contract, such as to
reflect changes in circumstances or to
improve the project’s performance.
—
Termination: Provisions for termination
of the contract, such as if one party is
in material breach of their obligations or
if the project is no longer economically
viable.
—
Notice: Provisions for notice specifying
the amount of time that a party must
give before suspending, modifying, or
terminating the contract and the means
of giving notice.
—
Justification: Provisions for justification
specifying the reasons a party can use
to suspend, modify, or terminate the
contract and the process the parties
must follow to consider the justification.
—
Compensation: Provisions for
compensation specifying the amount of
money a party may claim in the case of
suspension, modification, or termination
of the contract and the process of
claiming such compensation.
> Chapter 4: PPP Project Implementation and Execution
48
Manual on PPP projects, management and execution
Social impact analysis
Overview and objectives
Social impact analysis aims to identify and
analyze the impact of the project on the lives
Execution
48
Manual on PPP projects, management and execution
Social impact analysis
Overview and objectives
Social impact analysis aims to identify and
analyze the impact of the project on the lives
of people living and working in the area of
influence. The goal is to mitigate any adverse
impacts and fully consider them in the decision-
making process. Conducting a social impact
analysis can significantly lower the overall
risks associated with a project by decreasing
opposition, increasing support, and providing a
deeper understanding of the costs and benefits
of the project.
Process to follow:
The process of analyzing social impacts is
regulated in many countries as part of the
appraisal of infrastructure projects. However, the
project team must follow any legal or regulatory
rules applicable to the UAE. The typical process
involves:
1.
Identification of people residing and/or
working within a project’s area of influence,
including mapping of communities and their
social, economic, and cultural connection
with the site where the project will be
implemented and listing of social issues to be
considered.
F. Social, economic, and environmental analysis
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 - 4 months
Concerned
Federal Entity
The Ministry
At the end,
with all
studies
At the end,
with all
studies
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
48
economic effects
that result from the increased income and
spending of project employees and other
direct beneficiaries.
— Fiscal impacts: The effect on public
finances, including government revenues
and expenses, such as the tax revenues it will
generate and project-related costs.
— Quantitative analysis (GDP impact
calculation). See the example below:
Few examples on potential
Social Impacts to consider:
1. Displacement and resettlement of
residents and loss of livelihoods.
2. Changes in demographic status
and social cohesion.
3. Loss of cultural heritage or sacred
sites.
4. Loss of access to resources and
services.
5. Changes in community health
and well-being.
6. Changes in community economic
conditions.
7. Impact on community safety and
security.
8. Changes in community
perceptions of the project and its
developers.
> Chapter 4: PPP Project Implementation and Execution
50
Manual on PPP projects, management and execution
Environmental impact analysis
Overview and objectives
PPP projects can have both positive and negative
environmental impacts from construction
and operation and may also have secondary
impacts beyond the immediate project area
and people associated with it. These impacts
and the corresponding formal approval process
can cause delays in PPP projects. Mitigation
strategies for environmental risks imposed by
approving agencies can also affect project
costs and investment returns. A comprehensive
assessment of environmental issues in the
projects. Mitigation
strategies for environmental risks imposed by
approving agencies can also affect project
costs and investment returns. A comprehensive
assessment of environmental issues in the
appraisal phase is important to ensure they
are addressed and incorporated into project
decisions, and to anticipate, avoid, minimize,
or offset any adverse effects. Additionally,
some financial institutions have their own
environmental standards that may differ from the
formal approval process, so it’s good practice
to understand and include these in the appraisal
process to ensure the project is eligible for
financing.
Process to follow:
The environmental feasibility analysis is a crucial
step in a PPP project, as it aims to assess whether
any specific aspect of the project may make
environmental approvals difficult to obtain. To
approach this question adequately, four steps
are necessary:
GDP impact calculation –
Example of a PPP contract for a service
1.
Identification of all legal and regulatory
aspects relevant to obtaining the
environmental approvals. This includes
analyzing the institutional environment of
the country where the approvals will be
conducted, determining which agency is
responsible for approval, and understanding
the process, including any levels of approval.
2. Thorough due diligence effort to identify,
describe, and quantify the environmental
impacts of the project. This is often referred
to as an environmental impact assessment
any levels of approval.
2. Thorough due diligence effort to identify,
describe, and quantify the environmental
impacts of the project. This is often referred
to as an environmental impact assessment
and should be a formal report that addresses
the project’s environmental impact from
a comprehensive perspective, including a
full description of the area to be influenced
by the project, an analysis of the project’s
environmental impact on the area, and a
description of the physical and biological
aspects of the area after the construction and
operation of the infrastructure.
3. Definition of a strategy to mitigate the
specific effects of the project. This should
focus on the most significant environmental
effects and mechanisms to minimize them,
such as changes to the design of the
infrastructure or output specification, and
measures to compensate for inevitable
environmental consequences.
4. Obtaining, wherever possible, the
environmental permits and final approvals
needed for construction of the infrastructure.
It should be recognized that in many cases
it may not be possible to obtain the final
environmental approvals during the appraisal
phase.
Total impact on GDP
Direct impact on GDP
Indirect impact on GDP
Direct impact
on GDP
Corporate
profits
expenditure
Corporate
localization
factor
Annual
EBITDA
Wages
localization
factor
Wages
expenditure
Annual income
of staff
Indirect GDP
multiplier for public
administration
> Chapter 4: PPP Project Implementation and Execution
51
income
of staff
Indirect GDP
multiplier for public
administration
> Chapter 4: PPP Project Implementation and Execution
51
Manual on PPP projects, management and execution
Approaches to managing risk
Parties in a PPP project jointly bear and manage
the risks. Each party manages the risks it is more
experienced in handling. The following steps
optimize the allocation of responsibilities:
1.
Identify risks
The project team should identify the types
of risks that may arise during the project’s
life cycle. It should do so for all types of
risks faced by the stakeholders, mainly the
concerned federal entity, the private sector
player, and the ministry.
Table 7 lists some common risks encountered
during PPP projects. However, each project
is different and will, therefore, encounter
different types of risks.
Table 7: Common risks that arise during PPP projects
Identify risks
Evaluate risks
Mitigate risks and allocate
responsibility
1
2
3
E X A M P L E S O F R I S K S
Financing
Hiring
Inflation
Cultural change
Compliance
Demand fluctuation
Construction
Bankruptcy
Operational costs
Change in law
Data privacy
Political risks
Environmental risks
Social risks
Force majeure
G. Risk analysis
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 - 4 months
At the end,
with all
studies
At the end,
with all
studies
Concerned
Federal Entity
The Ministry
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
52
- 4 months circumstances organizational structure, and any respect to the change. TO FOLLOW in the figure below only in the entity, calling for expressions of interest as be carried out between the potential TO FOLLOW reinforcing the finality of this PROPOSAL OPENING information contained in the such as those relevant law. the erroneous procedure. To ensure the financial support and commitment of lenders to the project. loans obtained by the private regulatory risks exist. They These guarantees can essential clauses. A high-level framework and and administration: This component in the agreement. created by the PPP. Provides insights on Ensure compliance with the contract cause damage to this relationship, the two other important characteristics: an emphasis Appendix Optical fiber lines or networks may be through the urgent procedure meth to the public interest, provided that issues, majeure result from latent operation and as the for private partner must provide main partners working in the used in the project achieve success under Increased marketability validity and adher
At the end,
with all
studies
At the end,
with all
studies
Concerned
Federal Entity
The Ministry
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
52
Manual on PPP projects, management and execution
2.
Evaluation of risks
The project team should assess the
potential impacts of the identified risks,
which are typically based on historical
data and expert opinion.
To judge each risk, the project team
should estimate its size or impact and the
probability that it will occur.
3.
Mitigation and allocation of identified
risks
Some risks might require developing one
of three types of mitigation strategies:
avoid the risk completely, transfer the risk
from one entity to another; monitor the
risk and act when required. The main risks
associated with PPP projects and their
mitigation measures are detailed in the
appendix.
Table 8: Example of how to develop a risk assessment
Very
unlikely
Possible
Very
Likely
Likelihood
Impact
• Event is not foreseen to
occur (<1%), and no similar
events have been recorded
• Almost certain to occur
(>60 %) and has occurred
multiple times in similar
circumstances
• Expected to occur (10-30%)
and singular events have
been recorded
Likely
Unlikely
• Strong possibility to occur
(30-60%) under regular
project circumstances
Occurrence
Classification
• Will occur only under
exceptional circumstances
(1-10%) with low probability
Financial
Classification
Very
low
Moderate
Very
High
Occurrence
Classification
• Will occur only under
exceptional circumstances
(1-10%) with low probability
Financial
Classification
Very
low
Moderate
Very
High
AED 1M – 10M direct loss
High
Low
AED 10M – 100M direct loss
AED 0.1M – 1M direct loss
Other potential impact
specific to the project itself
(i.e., impact on number of
inspections carried in the
case of fire safety
inspections)
> Chapter 4: PPP Project Implementation and Execution
53
Manual on PPP projects, management and execution
The tendering plan structures the tendering
process and details each step of that process. It
should include the following sections:
Introductory section
1.
A summary of the PPP project, including the
need for the project, its objectives and how
they are achieved, technical elements, the
contracting model, and details of the risk
allocation.
2. A summary of the expected market for
the PPP project, including whether the
target market is local or international, the
advertising and marketing program, and any
other steps to be implemented according
to the approved tendering plan to attract
investors and engage concerned bodies.
Tendering Preparation
1.
The necessary preparations for tendering,
including the number of employees and
their roles, organizational structure, and any
outsourced advisory services.
2. Steps and schedule for the tendering
process, including the number of requests for
clarification, the schedule of activities, and
outsourced advisory services.
2. Steps and schedule for the tendering
process, including the number of requests for
clarification, the schedule of activities, and
responsibilities at each phase.
3. Detailed procedures and mechanisms
for tendering and the tendering method,
grounds, and budget.
4. Description of the provisions for
communicating with the private sector,
qualified investors, or bidders to enable them
to submit their proposals and documents.
Other sections
1.
Details of established evaluation procedures
and standards.
2. Tendering risks and how to reduce or mitigate
them.
3. The established method for adding
comments and amendments to the tender
documents, and the suggestions bidders are
permitted to submit in relation to alternative
technical concepts that might improve the
PPP project.
4. Expected budget for the tendering
procedures.
5. Draft tender documents, including notices,
general and special provisions for the
tendering process, the draft PPP project
contract, and any other documents attached
to the tender documents.
6. A statement about whether the tendering
plan and tender documents contain any
change to the data and information in the
business case documents or the approval
decision, and the actions and measures taken
with respect to the change.
H. Tendering plan
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 weeks
At the end,
with all
studies
At the end,
H. Tendering plan
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
2 weeks
At the end,
with all
studies
At the end,
with all
studies
Concerned
Federal Entity
The Ministry
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
53
Manual on PPP projects, management and execution
54
Manual on PPP projects, management and execution
I. Final analysis and submission
1.
2.
3.
4.
5.
The project team compiles all analyses
detailed throughout this section in
one document, then shares it with the
concerned federal entity, including the
template provided.
The concerned federal entity conducts
a detailed review of the study and
asks for any clarifications and/or
amendments, if any, otherwise it
shares it with the ministry.
The ministry reviews the study
according to the checklist provided
and shares comments and suggestions
to the concerned federal entity, if any.
If there is an impact on the budget, the
ministry first shares the study with the
general budget committee for initial
approval and then with the cabinet for
a final decision.
If there is no impact on the budget, the
ministry shares the study directly with
the cabinet for a final decision.
STEPS TO FOLLOW
The final document should
include:
— Project overview and strategic
objectives
— Current status of the asset or service
— Procurement alternatives, including
VFM and pros and cons of each
The final document should
include:
— Project overview and strategic
objectives
— Current status of the asset or service
— Procurement alternatives, including
VFM and pros and cons of each
— PPP models that are applicable and
the reasons for choosing one of them
— Technical due diligence
— Legal due diligence
— Financial due diligence
— Social, economic, and environmental
impact analyses
— Potential risks of the project
— Tendering plan
As part of the final deliverable,
the project team must fill out and
submit the templates provided.
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
1 week
Concerned
Federal Entity
The Ministry
1 month
General
Budget
committee
Cabinet
P02.
Feasibility
Study
Template
R02.
Feasibility
Study
Checklist
> Chapter 4: PPP Project Implementation and Execution
55
Manual on PPP projects, management and execution
IV. TENDERING AND PARTNER SELECTION
Documents
submission
Draft & share
invitation to tender
(ITT)
The project team drafts
the ITT document which
will then be reviewed,
marketed and shared by
the concerned federal
entity
Submit
qualification
documents
Evaluate
Evaluate submissions
and recommend most
qualified players
Evaluate
Evaluate submissions
and recommend best
bidders
Approval
Contact potential
private player, final
negotiations &
contracting
Selected player
signs contract
2
5
12
13
Draft & submit RFQ
The project team drafts
the RFQ which is then
shared by the
outlines the comprehensive tendering process
that must be adhered to for all PPP tenders, as
mandated by law. This process corresponds
to the “two-phased method,” which is the
recommended approach for all projects.
Nonetheless, there are two alternative methods
that can also be applied:
1.
The urgent procurement method: as per the
law, the offering may be through the urgent
procedure method, which consists of one
stage - without a qualification procedure. It
can be applied in any of the cases stipulated
in the law Article (15) clause 1.b.
—
If the concerned federal entity opts for the
urgent procurement method, it must seek
formal authorization from the ministry. This
request should include comprehensive
documentation or explanations justifying the
urgency or the absence of potential partners.
The ministry is required to provide an
official response within 20 days of receiving
the request, after which the procurement
process may commence.
—
In this case the procurement process starts
from step 8 of the describes process defined
below.
2. The direct appointment method: The offering
may be through the direct appointment
method, where the concerned federal entity
negotiates directly with one or more potential
partners. This method is used only in the
cases stipulated in the law article (15) clause
1.c.
—
In this case the concerned federal entity
directly starts negotiations with the potential
private partner after which the process
cases stipulated in the law article (15) clause
1.c.
—
In this case the concerned federal entity
directly starts negotiations with the potential
private partner after which the process
starts from step 10 of the described process
defined process.
—
Should the concerned federal entity choose
to proceed with the urgent procurement
Method or the direct appointment method,
it is required to submit an official request to
the ministry, accompanied by all relevant
documentation and explanations that
substantiate the request, aligning with the
stipulations outlined in article (15) clause 1.b.
or 1.c. of the law respectively. The ministry is
obligated to issue an official response within
a 20 days period following the receipt of this
request, and upon receiving this approval,
the entity may then initiate the procurement
process.
> Chapter 4: PPP Project Implementation and Execution
56
Manual on PPP projects, management and execution
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
N/A
1 week
Concerned
Federal
Entity
N/A
N/A
1 week
A. Invitation to tender and expression of interest
STEPS TO FOLLOW
Overview
An invitation to tender (ITT) for a PPP is a
marketing document issued by the concerned
federal entity, calling for expressions of interest
(EoIs) from potential private partners to partner
with the government on a certain project.
This process contributes significantly towards
(EoIs) from potential private partners to partner
with the government on a certain project.
This process contributes significantly towards
attracting better private sector participation in
the bid process for the project. It is useful to
discuss the project with prospective bidders and
understand their initial thinking and concerns in
participating in the procurement process, before
they submit their bids.
The EoI phase does not qualify or
disqualify any potential bidder.
1.
2.
3.
The project team develops the ITT
document, which should include the
sections detailed below:
—
A summary of the project and its
potential schedule.
—
A brief about the objectives
and scope of the work and the
expected deliverables.
—
Instructions on the nature of the
job, submission requirements, bid
processing fees (if any), and the
submission method and deadline.
—
Information about acceptable
formats for EoI submissions.
The concerned federal entity oversees
the marketing campaign, including
sharing the ITT with the public and
answering questions from interested
private sector partners.
Interested potential private sector
partners submit an EoI by an
advertised deadline.
To ensure transparency and fair competition,
the ITT should be heavily marketed to reach as
many potential players as possible and ensure
participation. This includes sharing through all
relevant websites and social media platforms.
> Chapter 4: PPP Project Implementation and Execution
many potential players as possible and ensure
participation. This includes sharing through all
relevant websites and social media platforms.
> Chapter 4: PPP Project Implementation and Execution
56
Manual on PPP projects, management and execution
57
Manual on PPP projects, management and execution
B. Pre-qualification
1.
2.
3.
4.
5.
6.
STEPS TO FOLLOW
Overview
The pre-qualification phase begins with the
concerned federal entity issuing an RFQ to
interested private partners. The private partners then
submit an SOQ. This part of the PPP procurement
process:
—
Verifies that the private partners have the
technical and financial qualifications to
implement the project effectively and to meet its
entire obligation under the contract.
—
Avoids wasting time in the final bid submission
phase by excluding inappropriate parties.
—
Filters participants to produce a small number of
high-quality final offers, which will reduce costs
and effort in the assessment phase.
Interested parties will have two weeks to submit a statement of qualifications (SOQ) once an RFQ is shared.
With this manual, an RFQ template has been issued detailing how to develop the RFQ, which
includes and defines bidding rules such as selection criteria and expectations from bidders.
The project team drafts an RFQ based on
the template provided with this manual.
The concerned federal entity reviews the
RFQ and shares it with the potential private
sector partners that have expressed their
private partners and the Concerned Federal entity
throughout the process, at the request of either party.
The contact number of a member of the concerned Federal
Entity working team will be included in the RFQ to enable this
line of communication
58
Manual on PPP projects, management and execution
C. Request for proposals
1.
3.
2.
4.
5.
6.
7.
The project team develops an RFP
template based on the template shared
in this manual.
The concerned federal entity reviews
the RFP and shares it with qualified
potential private partners.
Qualified potential private partners
create proposals (technical and
financial) based on criteria specified
in the RFP and submit them to the
concerned federal entity.
The project team reviews and
evaluates the proposals according to
the RFP criteria and recommends the
best bidder to the concerned federal
entity.
The concerned federal entity creates a
summary of the best bids and selected
bidder and presents it to the ministry
for review.
If there is an impact on the budget,
the ministry first shares the summary
to the general budget committee
for initial approval and then with the
cabinet for a final decision.
If there is no impact on the budget, the
ministry shares the summary directly
with the cabinet for a final decision.
STEPS TO FOLLOW
Overview
An RFP is sent to qualified bidders to gather information
that will help the concerned federal entity assess which
bidders are most qualified to carry out the project.
Overview
An RFP is sent to qualified bidders to gather information
that will help the concerned federal entity assess which
bidders are most qualified to carry out the project.
Discussions can be carried out between potential
private partners and the concerned federal entity
throughout the process, at the request of either party.
The contact number of a member of the concerned
federal entity working team will be included in the RFP
to enable this line of communication.
If the project team is unable to agree on the project
terms with best rated bidder (according to evaluation
results), then it has the right to stop the discussion with
the best bidder and move on to negotiate the project
terms and the project agreement with the following
bidders in descending order on the list of best bids.
The proposal for a project shall be submitted either by a
single partner from the private sector or from a coalition
of several potential private sector partners.
In the event that the offer is from a consortium of
partners, the offer must be submitted in the name of
the alliance, and it is prohibited for any of the members
of the alliance to submit offers individually, whether
directly or through another alliance, or to submit the
offer from a company in which one of the members
of the alliance owns the majority of its capital or has
control over its management, unless the terms of the
tender stipulate otherwise or with the approval of the
concerned federal entity.
submission in the procurement process.
5. Strict confidentiality: The project team
should uphold the confidentiality of BAFO
submissions, preventing the disclosure
of any bidder’s offer to competitors, thus
maintaining the integrity of the competitive
process.
6. After BAFOs are received, reviewed, and
scored: the process continues from step 5.
Relevant documents
1.
Request for proposal
— A tender document issued to bidders by the
concerned federal entity requesting proposals in
relation to a PPP project. The RFP enables the con
cerned federal entity to gather detailed information
from qualified bidders to help determine which
bidder is best suited — technically and financially —
for the project.
2. Proposal
— Documents submitted by bidders to the concerned
federal entity in response to an RFP for a PPP
Project (A proposal template is usually included in
the RFP).
Government
Bidders
Government
Bidders
Specialized committees may be created at
the discretion of the project team to help
with the evaluation process, if needed.
These might include a financial proposal
evaluation committee, a technical proposal
evaluation committee or a proposal opening
committee.
Responsibilities of the project
team & concerned federal
entity in review and selection
1. PROPOSAL OPENING
—
Receives all technical and financial proposals.
—
Ensures all expected proposals and related
documents have been received. Records the
names and number of documents, and the
—
Receives all technical and financial proposals.
—
Ensures all expected proposals and related
documents have been received. Records the
names and number of documents, and the
date and time they were received.
—
Invites bidders to attend the proposal opening
event, if required by the approved tendering
plan and the RFP.
2. TECHNICAL PROPOSAL EVALUATION
—
Prepares a checklist of the documents, data,
and other information that must be provided
in the technical proposals, based on the
requirements of the RFP.
—
Receives and reviews technical proposals and
confirms their completeness based on the
requirements of the RFP.
—
Prepares a report identifying whether each
proposal is complete or incomplete, and
identifies the missing items based on the
checklist.
3. FINANCIAL PROPOSAL EVALUATION
—
Evaluates complete financial proposals.
—
Carries out a detailed assessment of the
strengths and weaknesses of the financial
proposals, according to the evaluation criteria,
and identifies any required clarifications.
—
Classifies the evaluated financial proposals
as either successful or unsuccessful. If the
approved tendering plan and RFP contain
other classifications, the proposals are
classified accordingly.
—
Prepares an evaluation and classification
report.
—
Clarifies information contained in the
proposals based on the approved process and
schedule.
—
Updates the evaluation report, identifying any
changes to the classification of proposals.
proposals based on the approved process and
schedule.
—
Updates the evaluation report, identifying any
changes to the classification of proposals.
> Chapter 4: PPP Project Implementation and Execution
60
Manual on PPP projects, management and execution
D. Awarding a PPP project
Steps to follow
The PPP project agreement is drafted by the
project team and reviewed by the concerned
federal entity and by the ministry and awarded to
the selected bidder. The project team informs all
bidders of the result of the selection process.
The preferred partner should be announced
20 days after all proposals are reviewed and
evaluated.
Some provisions of the project agreement:
(please refer to the project agreement template
issued with this manual to have the detailed
provisions)
Technical requirements, performance
requirements, environmental & social
requirements, performance guarantee,
insurance requirements, time requirements,
reporting obligations, monitoring provisions,
financial structure provisions and regulations,
payments mechanisms, force majeure definition
and impact, dispute resolution procedures,
termination provisions, compensation for
termination, relief from termination, extension,
renewal, amendment, stalled projects etc...
All these rules and provisions, such as those
regulating change of control, exceptional
circumstances, termination of contract,
arrangement of mortgages on assets, etc... are
unique to each project and should be detailed
regulating change of control, exceptional
circumstances, termination of contract,
arrangement of mortgages on assets, etc... are
unique to each project and should be detailed
in the project agreement as agreed between
both parties and with the help of the template
provided.
When negotiations are required, the concerned
federal entity should:
1.
Form a negotiations team composed of
the project team and additional advisors,
if required. Team members should be
experienced in the expected negotiation
subjects and the PPP project details.
2. Request that the preferred bidder and the
reserve bidder(s), if necessary, extend their
guarantees to cover the matters agreed upon
during the negotiations.
3. Determine the place, date, and time for final
negotiations and set a detailed schedule for
such negotiations, taking into consideration
the requirements of the bid guarantee.
4. Communicate with the preferred bidder with
respect to the details and requirements of
the final negotiations.
Post contract award and prior to financial close, a Project
company (SPV) must be created by the private sector partner(s)
Owner
Supporting
tool
Time to
develop
Reviewer
Supporting
tool
Time to
review
Approver
Project
Team
PA1_Project
Agreement
Template
PA1_Project
Agreement
Template
1 month
Concerned
Federal
Entity
The Ministry
2 weeks
General
budget
committee
Cabinet
> Chapter 4: PPP Project Implementation and Execution
61
Manual on PPP projects, management and execution
The committee is formed within the ministry of
finance to decide on grievances related to the
tendering procedures of PPP bids. One or more
members from the concerned federal entity
involved in the grievance will be invited.
These members will be appointed by the
committee’s chairman, based on the nomination
from the head of the concerned federal entity or
their delegate.
Appealing process:
1.
Any bidder who participated in the bid may
submit a grievance request to the ministry
within 10 days of the results announcement.
The request must include detailed reasons
and supporting documents explaining why
the bidder believes their chances were
minimized.
2.
The ministry’s grievances committee will
thoroughly review the submitted grievance
and decide on the matter within 30 working
days from the date of receipt, with the
possibility of an additional 15 working days
extension.
The committee may suspend the tendering
procedures until the grievance is decided
if it deems that continuing the tendering
procedures would significantly weaken the
appellant’s chances of winning the bid.
3.
If the grievances committee finds that the
reasons for the grievance are valid, it will
issue its recommendations on the grievance,
which may include one of the following
actions:
—
Correcting the erroneous procedure.
—
Excluding one of the bidders.
—
Taking any other necessary actions.
—
Rejecting the grievance for lack of valid
reasons.
The committee will submit its
—
Excluding one of the bidders.
—
Taking any other necessary actions.
—
Rejecting the grievance for lack of valid
reasons.
The committee will submit its
recommendations to the minister for
approval before taking any action.
62
Manual on PPP projects, management and execution
E. Commercial and financial close
Once the tendering process is complete, and
after the necessary approvals are obtained and
the relevant documents have been updated
to clearly articulate the business case, the
concerned federal entity must sign the contract
and work to fulfil any conditions that must
precede the start of the project. It must:
—
Ensure all approvals necessary for awarding
and signing the contract have been
obtained.
—
Prepare and complete the PPP project
documents.
—
Determine the date and place the PPP project
documents will be signed and coordinate
with the successful bidder.
—
Enable parties to sign the contract.
—
Prepare protocols for financial and
commercial closure.
—
Complete procedures for financial closure of
the PPP project, including any amendments
to the financial model, and changes to
the contract to reflect the final financing
conditions.
—
Commence implementation of the PPP
project and fulfilment of the condition’s
precedent, including issuing performance
bonds (if any).
Commercial closure
Commercial close is the event that occurs when
the concerned federal entity and the private
sector partner have reached an agreement on
> Chapter 4: PPP Project Implementation and Execution
63
Manual on PPP projects, management and execution
Guarantees (written pledges) provided by
the federal entity
Following the conclusion of the tendering
phase, the government often extends various
types of guarantees to the private sector. These
guarantees serve multiple purposes: facilitating
the project’s access to commercial financing,
enhancing competition among bidders by
mitigating project risks, broadening the investor
pool, and safeguarding the project’s financial
sustainability.
These guarantees fall into three primary
categories:
1.
Performance guarantees: Performance
guarantees are the most prevalent and vital
guarantees employed in PPPs. They act as
assurances to the private partner on behalf
of the relevant government entity that the
government’s allocated risks will be managed
as stipulated. These guarantees should be
customized based on a comprehensive risk
assessment:
—
Regulatory guarantees: shield the private
sector from liability arising from regulatory
issues or external factors, such as changes in
regulations beyond their control.
—
Political guarantees: protect the private
sector from liabilities resulting from political
shifts that could impact the PPP’s structure.
—
Early termination Guarantees: ensure that
the private sector is not held responsible
for early terminations initiated by the public
entity.
—
sector for project financing, often resulting
in more favourable terms.
—
Credit enhancement: governments may
provide credit enhancements to improve the
private partner’s creditworthiness, which can
lead to lower borrowing costs.
—
Service payment guarantees: these
guarantees ensure the timely payment of
debt service by the private partner, reducing
lender risk.
> Chapter 4: PPP Project Implementation and Execution
64
Manual on PPP projects, management and execution
When to choose each type of guarantee:
The choice between these methods should be
based on a careful assessment of the project’s
specific needs, risk factors, and financing
requirements.
The ministry can decide which type of guarantee
to provide at its own discretion, with a few
considerations for each type of guarantee:
1. Performance guarantees (preferred model):
When the project requires risk mitigation:
Performance guarantees are advisable when the
project involves significant risks that need to be
managed. These guarantees help ensure that
the private sector partner meets its contractual
obligations, which is crucial for project success.
For complex infrastructure projects:
Performance guarantees are suitable for
complex infrastructure projects where various
operational and regulatory risks exist. They
provide assurance that the private partner will
handle these risks effectively.
In projects with uncertain revenue streams:
If the project’s revenue streams are uncertain
provide assurance that the private partner will
handle these risks effectively.
In projects with uncertain revenue streams:
If the project’s revenue streams are uncertain
or dependent on factors beyond the private
partner’s control (e.g., demand fluctuations),
performance guarantees can provide financial
security.
2. Letter of Comfort:
When legal commitments are limited:
A Letter of comfort may be advisable when
the government wants to provide a level of
assurance to investors or lenders without
entering into legally binding guarantees. This
can be suitable when the government’s legal
commitments are restricted.
For projects with lower risk profiles:
In projects with relatively lower risks, where
comprehensive guarantees may not be
necessary, a Letter of Comfort can offer a more
flexible and less financially binding form of
support.
To attract equity investment:
A Letter of comfort can be used to attract equity
investors who may be less concerned with
guarantees but still seek government support.
2. Financial guarantees (least favourable):
When attracting private financing:
Financial guarantees are advisable when the
project aims to attract private financing, such
as loans from banks or investments from
institutional investors. These guarantees can
enhance the creditworthiness of the project.
For projects with high capital requirements:
Projects that require substantial upfront
capital investments may benefit from financial
enhance the creditworthiness of the project.
For projects with high capital requirements:
Projects that require substantial upfront
capital investments may benefit from financial
guarantees to secure favourable financing terms
and lower interest rates.
To share financing risks:
Financial guarantees can be used to share
financing risks between the government and
the private sector, making the project more
appealing to potential investors.
> Chapter 4: PPP Project Implementation and Execution
65
Manual on PPP projects, management and execution
V. CONTRACT MANAGEMENT
The final stage in a PPP project is contract
management, initiated after the commercial
and financial closure has been achieved.
During this stage, the concerned federal entity
assumes full responsibility for managing the PPP
contract with the private sector partner for the
agreed-upon duration outlined in the contract.
Each federal entity, following the governance
structure established during the feasibility study,
customizes the management process to suit the
specific characteristics, length, and expertise
requirements of the project, and thus there
is no unified or specific process to contract
management. However, the project agreement,
which is supplemented by this manual, includes
all essential clauses. A high-level framework and
main roles have also been detailed in Section
(b) of this chapter. All provisions that define the
contract such as termination, change of partner,
main roles have also been detailed in Section
(b) of this chapter. All provisions that define the
contract such as termination, change of partner,
exceptional circumstances are covered in the
project agreement template shared with this
manual.
A. Importance of Contract
Management
A tangible contract management function
helps manage obligations effectively, saving
time and resources for both parties and
providing benefits for business strategies and
procedures. Contracts are essential for key
business strategies and relationships, but many
parties fail to properly monitor and oversee
the implementation of contracts and fulfil their
obligations, resulting in missed savings, heavy
fines, costly litigation, and broken relationships.
Effective contract management ensures
better relationships, enforces compliance, and
mitigates risk, particularly in PPP contracts,
which have a long time span, requiring
substantial work and services with significant
complexities. Proper project monitoring enables
the government to understand project issues and
for savings to be achieved and shared between
parties. Both the government and private partner
should be familiar with contract management
procedures to enhance the efficiency and
success of the PPP project. Communication
and knowledge sharing of existing PPPs is
important for identifying improvements for
future contracts, creating a virtuous cycle of
collaboration.
success of the PPP project. Communication
and knowledge sharing of existing PPPs is
important for identifying improvements for
future contracts, creating a virtuous cycle of
collaboration.
> Chapter 4: PPP Project Implementation and Execution
66
Manual on PPP projects, management and execution
B. Contract Management
Framework
Contract management in PPP projects refers to
the processes and procedures that are put in
place to ensure that the terms of the contract
between the public sector and the private sector
are met. This includes:
1. Establishing governance and the contract
management team: The establishment of
governance and contract management
functions by the government during the
early stage of a project will unlock numerous
benefits including the reduction of chances
of possible pitfalls.
2. Contract preparation: This includes activities
such as project planning, procurement, and
contract negotiation. It is designed to ensure
that the project is properly structured and
that the contract is legally and financially
sound.
3. Contract execution: This component includes
activities such as mobilizing resources,
starting construction, and delivering goods
and services. It is designed to ensure that
the terms of the contract are carried out as
agreed upon.
4. Contract administration: This component
includes ongoing management of the
contract throughout the life of the project.
It includes activities such as ensuring that
payments are made on time, monitoring
includes ongoing management of the
contract throughout the life of the project.
It includes activities such as ensuring that
payments are made on time, monitoring
compliance with the contract, and
coordinating communication between the
parties.
5. Performance monitoring: This component
includes the process of assessing the
performance of the private partner against
the terms of the contract. It includes
evaluating the quality of goods and services
provided, measuring compliance with
performance targets, and assessing customer
satisfaction.
6. Resolution of disputes: This component
includes the process of resolving any
disagreements or disputes that may arise
between the public and private partners.
It can include mediation, arbitration, or
litigation and the goal is to reach a fair and
mutually acceptable resolution.
The goal of contract management is to ensure
that the project is completed on time, within
budget, and to the satisfaction of all parties
involved.
From the perspective of concerned federal
entity, contract management is important for:
—
Verifying that the private partner is
fulfilling their obligations according to the
agreement.
—
Ensuring that the project is being carried out
and operating at the minimum service levels
outlined in the agreement.
—
Avoiding any financial loss to the public
entity.
From the perspective of private partners,
contract management is important for:
—
Ensuring that the public entity is also
—
Avoiding any financial loss to the public
entity.
From the perspective of private partners,
contract management is important for:
—
Ensuring that the public entity is also
meeting its obligations as outlined in the
agreement.
—
Having a means to raise any concerns or
issues in the execution of the project.
> Chapter 4: PPP Project Implementation and Execution
67
Manual on PPP projects, management and execution
I.
ESTABLISHING THE CONTRACT
MANAGEMENT TEAM
The effectiveness of a PPP in generating
value for money is determined by the
capabilities of the private partner and
the government’s contract management
systems and teams. This is particularly
relevant in PPP contracts that include
government risk retention, such as a
minimum revenue guarantee or other
contractual agreements. However, the
establishment of a contract management
team will not, in itself, guarantee that the
government will maximize the value for
money of the PPP contract.
The specifics of the mandate, contractual
standing, and resources required will
differ from sector to sector and even from
one project to another. Factors that will
influence these functions are as follows:
—
Scale of a project or program of
projects: A useful metric is the value of
the assets created by the PPP.
—
Administrative complexity of the
projects, such as whether they are
cross-border or cross-agency in
jurisdiction.
—
Extent of risk retained by the
government in terms of the PPP
—
Administrative complexity of the
projects, such as whether they are
cross-border or cross-agency in
jurisdiction.
—
Extent of risk retained by the
government in terms of the PPP
agreement (which can be determined
by considering the financial
consequences accruing to the
government of a risk materializing).
PPP contract governance structure requires
various layers of interaction between the
two parties.
After the tendering and partner selection
phase, the concerned federal entity, before
the project team is dissolved, will assign a
contract management team.
The contract management team, typically
organized at a sectoral level, may oversee
multiple PPP projects. It’s beneficial to
outline the typical team composition, along
with the high-level roles and responsibilities
of each member. This includes, but not
limited to:
—
Project Manager: Oversees the entire
project, ensuring that contractual
obligations are met and managing
communication between stakeholders.
—
Financial Analyst/Manager: Handles
financial aspects, including budget
management, financial reporting, and
ensuring economic viability.
—
Legal Advisor: Advises on legal matters,
ensuring the contract complies with
laws and regulations and handles any
legal disputes.
—
Technical Expert: Provides insights on
the technical aspects of the project,
ensuring that technical requirements
are met.
—
Risk Manager: Identifies, assesses,
and mitigates risks associated with the
project.
—
the technical aspects of the project,
ensuring that technical requirements
are met.
—
Risk Manager: Identifies, assesses,
and mitigates risks associated with the
project.
—
Quality Assurance Manager: Ensures
that the project’s deliverables meet the
quality standards and requirements
outlined in the contract.
—
The team must be formed by the
concerned federal entity before the
award and execution of the project.
Public – Private Partnerships Manual
> Chapter 4: PPP Project Implementation and Execution
67
Manual on PPP projects, management and execution
68
Manual on PPP projects, management and execution
II. CONTRACT PREPARATION
Includes the process leading up to contract
execution, starting from the date of the
letter of award to the commencement
of construction consisting of all pre-
construction project activities such as land
acquisition, and obtaining the required
licenses:
i.
Ensure that the private sector has
received the required funding – if
applicable – and is financially ready to
take on the project.
ii.
Ensure that any needed assets have
been purchased or transferred as per
the contract agreement such as lands
or buildings.
iii. Ensure that the private party has all the
required technical approval to proceed
with the project.
iv. Ensure compliance with the contract
agreement.
v.
Other roles might be required for this
phase depending on the project.
I.
CONTRACT EXECUTION
Contract execution in PPP projects refers to
agreement.
v.
Other roles might be required for this
phase depending on the project.
I.
CONTRACT EXECUTION
Contract execution in PPP projects refers to
the process of carrying out the terms of the
contract as agreed upon by the parties. It
includes all the activities that are needed to
start and complete the project and deliver
the goods and services as outlined in the
contract.
i.
The private partner should mobilize
the necessary resources, such as
equipment, personnel, and materials to
start the project.
ii.
The private partner should submit
a detailed project execution plan,
outlining the resources, milestones,
deliverables, and timelines for the
project, to be approved by the
concerned federal entity.
iii. The private partner should start
construction or delivery of goods
and services according to the project
execution plan and the contract.
iv. The private partner should ensure that
all necessary permits and approvals are
obtained before starting the project.
v.
Both the private party and the
concerned federal entity should
complete all conditions mentioned
in the PPP Contract prior to contract
execution.
vi. The private partner should coordinate
with the concerned federal entity to
resolve any issues or challenges that
may arise during the execution phase.
vii. The private partner should follow all
safety, environmental, and quality
standards outlined in the contract.
viii. The private partner should submit
a matter that may adversely affect the
progress of the whole project. Therefore,
it is necessary to identify a mechanism
for settling disputes arising from the PPP
contract. A legal consultant may be sought
in this matter.
The agreed mechanism for dispute
settlement is an important element in
identifying the PPP contract risks by the
private partner. Therefore, it is necessary
to build the relevant private partners’
confidence that there is a fair system for
dispute settlement to encourage them to
participate in these projects. Preferably,
the disputes shall be settled by resorting
to any of the available dispute settlement
mechanisms which are in compliance
with international best practices, without
resorting to legal proceedings that are long
and costly in nature.
Methods of Dispute Settlement
1.
Negotiation: the most commonly used
form of dispute resolution where the
parties come together to discuss a
mutually agreeable settlement.
2. Mediation: involves negotiations with the
support of an independent third party. It
has the benefit of balanced inputs from a
neutral third party.
3. Arbitration: Arbitration procedures are
outlined in the contract. They involve the
process of resolving disputes in which
both sides agree to be bound by the
decision of a third party, the arbitrator.
The decision of the arbitrator is binding
on the contracting parties.
4. Expert Determination: useful when it
is a technical issue. In a typical expert
decision of a third party, the arbitrator.
The decision of the arbitrator is binding
on the contracting parties.
4. Expert Determination: useful when it
is a technical issue. In a typical expert
determination, the parties would agree to
be bound by the expert’s decision.
5. Litigation: court process of resolving the
dispute.
> Chapter 4: PPP Project Implementation and Execution
71
Manual on PPP projects, management and execution
APPENDIX
71
Manual on PPP projects, management and execution
72
Manual on PPP projects, management and execution
The Organization for
Economic Co-operation
and Development (OECD)
An agreement between the government and one or
more private partners (which may include the operators
and the financers). Within the agreement, the private
partners deliver the service so that the service delivery
objectives of the government are aligned with the profit
objectives of the private partners. Furthermore, the
effectiveness of the alignment depends on a sufficient
transfer of risk to the private partners.
International Monetary
Fund (IMF)
Arrangements in which the private sector supplies
infrastructure assets and services that traditionally have
been provided by the government. In addition to private
execution and financing of public investment, PPPs
have two other important characteristics: an emphasis
on service provision and investment by the private
sector. In this way, significant risk is transferred from the
government to the private sector.
on service provision and investment by the private
sector. In this way, significant risk is transferred from the
government to the private sector.
The European Commission
(EC)
The term Public-Private Partnership is not defined at the
community level. In general, the term refers to forms of
cooperation between public authorities and the world of
business which aim to ensure the funding, construction,
renovation, management and maintenance of
infrastructure for the provision of a service.
European Investment Bank
(EIB)
Public-Private Partnership is generic term for the
relationships formed between the private sector and
public bodies, often with the aim of introducing private
sector resources and/or expertise in order to help
provide and deliver public sector assets and services.
The term PPP is thus used to describe a wide variety
of working arrangements from loose, informal and
strategic partnerships, to design, build, finance and
operate (DBFO)-type service contracts and formal joint
venture companies.
Standard and Poor’s (S&P)
Any medium- to long-term relationship between the
public and private sectors involving the sharing of risks
and rewards of multi-sector skills, expertise and finance
to deliver desired policy outcome.
> Appendix
ANNEX 1
DIFFERENT PPP DEFINITIONS
73
Manual on PPP projects, management and execution
Sectors in which an asset or service may
be procured under a PPP Scheme
TYPE
SECTOR
EXAMPLES
Economic
ANNEX 1
DIFFERENT PPP DEFINITIONS
73
Manual on PPP projects, management and execution
Sectors in which an asset or service may
be procured under a PPP Scheme
TYPE
SECTOR
EXAMPLES
Economic
Transport
Roads
— New road/highways
— Specific tunnel or bridge projects
— Access links (for instance, to ports)
— Upgrading and expansion of roads and network
Economic
Transport
Rail
— High-speed rail lines
— Heavy conventional rail lines
— Rapid links (for instance, to airports)
— Operational leasing of rolling stock
— Metro and other mass transit projects
— Ticketing and fare collection systems
— Metro stations
Economic
Transport
Other Urban Mobility Infra
structure
— Bus rapid transit infrastructure
— Parking
— Intermodal interchange or hubs
Economic
Transport
Ports and Airports
— New or upgraded airports
— New or upgraded ports
Economic
Water and Waste
— Desalination plants
— Wastewater treatment plants (WWTP)
— Integrated water cycle concessions
— Solid waste management systems
— Waste to energy plants – incineration plants
Economic
Energy
— Independent power producer plants through
PPAs
— Electricity transmission lines
— Gas pipelines
— Energy efficiency (for instance, in public
buildings or in urban lighting)
Economic
Information and Communi
cations Technology (ICT)/
Telecommunications
— Optical fiber lines or networks
— Telecommunications networks/broadband
Economic
Tourism
— National parks
— Cultural heritage buildings
Economic
Agribusiness
— Grain storage PPPs
— Telecommunications networks/broadband
Economic
Tourism
— National parks
— Cultural heritage buildings
Economic
Agribusiness
— Grain storage PPPs
— Irrigation projects
> Appendix
ANNEX 2
SECTORS WITH PPP PROJECTS
74
Manual on PPP projects, management and execution
Social
Health, Education, Security/
Prisons, Courts/Justice, So
cial Housing
— Hospitals
— Student residences
— University facilities
— School facilities
— Court buildings
— Prison facilities
— Social housing
Social
Sports, Emergency Re
sponse, Local Security, gov
ernment Accommodations
— Sport centers
— Fire stations
— Police stations
— Government offices
> Appendix
ANNEX 3
FINANCIAL FEASIBILITY CASE STUDY
75
Manual on PPP projects, management and execution
Article (15)
Offering Methods and Procedures
1. The offering of Partnership Projects shall be according to one of the following methods:
a) Two-phase Method: The offering shall be as follows:
1) Phase 1: During which, a group of private sector entities that have expressed inter
est in the Project are pre-qualified.
2) Phase 2: During which, the full offering documents will be issued exclusively to the
potential partners who have been qualified.
b) Urgent Procedure Method: The offering may be through the urgent procedure meth
od, which consists of one stage - without a qualification procedure - in any of the fol
lowing cases:
1) There is a need to submit the Project urgently.
od, which consists of one stage - without a qualification procedure - in any of the fol
lowing cases:
1) There is a need to submit the Project urgently.
2) If the project team finds that there is no need to conduct qualification in the event
that there are a limited number of suitable potential partners in the market or the
absence of a complex technical aspect of the Project, which makes the competition
limited to financial aspects only, or for any other reason that does not require the
qualification of partners.
c) Direct Appointment Method: The offering may be through the direct appointment
method, where the Concerned Entity negotiates directly with one or more potential
partners, while this method is used only in the following cases:
1) The need to urgently provide assets or provide a service that is not compatible with
the use of the procedures specified in Paragraphs (a) and (b) of Clause (1) of this
Article.
2) The presence of one potential partner in the market with the ability to implement
the Project.
3) The connection or relevance of some or all of the components of the Project to na
tional security, defense security, or the protection of state secrets.
4) Any other necessary and urgent matters related to the public interest, provided that
the Minister agrees to use this procedure to submit the same.
2. In the event that there is only one potential partner for the Project, the Concerned Entity
the Minister agrees to use this procedure to submit the same.
2. In the event that there is only one potential partner for the Project, the Concerned Entity
may terminate the bid or continue with the offering and award the Project to the potential
partner, provided that the requirements of the offering documents are observed and there
is evidence of sufficient value for money in the offer to achieve value-for-money evaluation.
3. The PPP Manual specifies the procedures for each of the offering methods mentioned in
this article.
> Appendix
ANNEX 4
PPP LAW ON OFFERING METHODS
76
Manual on PPP projects, management and execution
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Failure to
provide
services in the
manner agreed
upon under the
contract
The services provided
by the private sector
may not meet the
required conditions
or conform to the
specifications issued
by the governmental
authority responsible
for providing the
service
Putting clear and accurate
outputs of the specifications
Monitoring the performance
Imposing penal deductions from
the payments released per unit/
for each unit separately
Private Sector
Partner
Project
completion risk
The completion of the
project may be delayed
due to construction
delays, design issues,
unforeseen events or
funding complications
Providing special insurance
coverage (against the delay in
the project execution)
Appointing an independent and
specialized entity to approve the
unforeseen events or
funding complications
Providing special insurance
coverage (against the delay in
the project execution)
Appointing an independent and
specialized entity to approve the
project completion
Liquidating damage,
construction warranties and
other appropriate warranties
provided by the private partner
as incentives for project
completion, unless the Federal
Entity sponsoring the project is
responsible for the delayed in
completion
Private Sector
Partner – unless
delay is attributed
to events of force
majeure or the
Federal Entity
sponsoring the
project
Exceeding
scheduled cost
The actual costs of
the project during
phases of design and
construction may
exceed the expected
costs of the project
as per its feasibility
studies
Drafting construction contracts
with fixed prices
Developing conditions relating to
emergency plans
Providing alternate credit
facilities / liabilities pertaining to
rights of additional shares paid
in advance and expected in the
financial model of basic cases
Private Sector
Partner
> Appendix
ANNEX 5
TYPES OF RISKS
77
Manual on PPP projects, management and execution
> Appendix
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Design-related
risks
The design developed
by the private partner
may be inconsistent
with the specifications
of project outputs
Preparing clear specifications for
the project outputs
Defining the responsibilities for
clear and latent defects
Consulting the responsible
or circumstances beyond the
reasonable control of both
parties
Shared between
Public and Private
Sector Partners
Inflation Risks
Actual inflation rates
may be greater than
expected ones.
Link inflation indicators
to payment calculations
considering worst case scenarios
as per WB or IMF projections.
Add clause in PPP contract
stating that payments should
be reviewed in case inflation
surpasses the forecasted rate by
a certain percentage.
An agreement
should be made
between both the
Public and Private
Sector Partners
on inflation of the
agreed upon rates,
and what so exceeds
shall be afforded by
the Private Partner
78
Manual on PPP projects, management and execution
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Risks related to
the cancellation
of partnership
or liquidation
and dissolution
of the private
partner
The Private Company
may be dissolved or
liquidated
Establishing a unit with specific
purposes to manage project cash
flows/ liquidity
Providing insurance cover
and warranty for the project
necessary assets
Setting restrictions on the
Private Sector partner regarding
indebtedness and credit and
finance restrictions
Obligations of notification
regarding the financial data and
information and judicial lawsuit
or dispute with creditors
Replacing private partner by
another new one by virtue of a
direct agreement
Private Sector
Partner
Risk of
Insurances
Any risk insurable at
the time of signing the
project contract under
agreed insurance
defects or deficiencies
hidden in the fittings
and facilities, including
the project assets
Facilities must be designed
and constructed by the private
partner unless the project
requires handing over the
currently existing facilities to
the private partner. In such
case bidders must perform due
diligence through conducting
extensive studies and necessary
inspection of facilities so
that it be possible to detect
shortcomings. As for the
procedures and costs pertaining
to the detected shortcomings,
a prior agreement may be
concluded with the Private
Partner about them. The Private
Partner should immediately
report the detected defects
If the private
partner assumes
the works of design,
it shall bear the
consequences of the
risk Otherwise, the
sponsoring Federal
Entity shall bear the
same, provided that
there is no insurance
coverage sufficient
to mitigate the
consequences of
such risk.
Maintenance
Risks
The maintenance
necessary for keeping
assets in a proper
condition for providing
the required services
may require higher
costs than those set
out in the project
prospections or
maintenance may be
not conducted at all
Preparing clear specifications for
the project outputs
Applying a system of penalties
and performance monitoring
Preparing an operation and
maintenance contract includes
and satisfies all the requirements
of the sponsoring Federal Entity
The sponsoring Federal Entity
shall preserve its right to replace
the Private Partner
maintenance contract includes
and satisfies all the requirements
of the sponsoring Federal Entity
The sponsoring Federal Entity
shall preserve its right to replace
the Private Partner
Providing a special insurance
coverage and warranties in
the form of final warranties of
maintenance
The Private Sector
Partner
Risks related
to supply
and demand,
service size
or market
mechanism
Demand for the
services provided
under the project may
be below expectations
or the desired rate
(for example, absence
of the need for such
services, expiry or low
level of their demand,
market competition
or the objection of
clients to the services
provided by the main
external partners)
For PPP projects in which the
payments are made per unit,
payment must be based on the
availability of service (not on
the basis of actual usage by the
Federal Entity sponsoring the PPP
project)
Applying effective plan with clear
objectives to market the services
in question
For the projects
financed on the
basis of payment per
unit, the sponsoring
Federal Entity shall
be responsible. For
the projects financed
by charging fees on
the project users or
beneficiaries, the
private partner shall
be responsible
80
Manual on PPP projects, management and execution
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Operation risks
All factors that
may affect the
project operation
requirements,
including the expected
costs of operation,
the required skills of
operation and alike
(except for force
requirements of cities
planning and urban
planning) or with any
other requirements
or approvals needed
under the foregoing
Or
Delay or failure to
obtain the necessary
approvals or even if
such approvals are
obtained, the project
will be executed at
a cost much higher
than the original costs
expected under the
project plans
The competent Federal Entity
must show all necessary
approvals on the detailed
proposal of design, building
and constructions in the project
regarding the large scale
planning so in order to identify
conflicts in the feasibility study
of the project. The approvals
include all approvals relate to the
land utilization and identification
of areas. The approvals must
be obtained before offering the
project in the bid.
The private partner shall identify
all cases of planning needed in
the
project and require the
competent authorities’ approval
regarding the proposal of design
and constructions of the project,
which authorities must take all
procedures and precautions
and include the same in their
work schedule to arrange for the
obtainment of approvals from the
above authorities.
For any approval on
area identification
and land utilization,
the Federal Entity
sponsoring the
project shall be
held liable for the
risk, unless the
Private partner is
responsible for
selecting the project
site.
For all approvals
on any identified
planning, design,
constructions and
buildings, the Private
Partner shall be held
liable
Systemic risks/
risks related
to practical
selecting the project
site.
For all approvals
on any identified
planning, design,
constructions and
buildings, the Private
Partner shall be held
liable
Systemic risks/
risks related
to practical
measures
The federal entities
or any governmental
authorities may take
unexpected acts that
have a severe negative
effect on the expected
revenues from the
rights of contributing in
the project or service
of debts and credit, or
in any way results in
increasing the costs
incurred by the private
partner.
Determine the risk of the
unexpected behaviors and acts
that have no other output in the
agreement of PPP and determine
the risk of the behaviors that
result in expropriation.
Distinguish between the general
and discriminatory acts. For the
unexpected discriminatory acts,
a special compensation shall be
granted.
As for the acts that result in
expropriation, the project shall
be ended and compensation
shall be granted.
For any unexpected
discriminatory act
or any act results
in expropriation of
public interest for
example, the Federal
Entity sponsoring the
project shall be held
liable for such risk.
As for the
unexpected public
acts, the private
partner shall be held
liable
82
Manual on PPP projects, management and execution
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Organizational
risks
The necessary approval
may be delayed or
cannot be obtained, or
even if such approval
is obtained, the project
will be executed at
a cost much higher
than the original costs
a guarantee to the Federal Entity
responsible for the project. The
guarantee may be, for example,
in the form of final guarantees of
maintenance or deductions from
the payments made on the basis
of units.
The private partner
Risks of inputs
or resources
Shortage of supplies
related to the project’s
inputs or resources
(including financial
credits) may occur, or
there may be inability
to provide the supplies
needed to operate the
project, including the
defects related to the
level of quality of the
available resources.
Concluding supply contracts to
fulfil the project requirements,
such as the contracts based on
direct supply for immediate pay
ment
Taking prompt actions of as
sistance only in the event of
shortcomings not falling under
the responsibility of the private
partner.
The private partner,
unless the inputs are
obtained from the
Federal Entity spon
soring the project
> Appendix
83
Manual on PPP projects, management and execution
> Appendix
RISK TYPE
DESCRIPTION
MITIGATION STRATEGY
RESPONSIBLE EN
TITY
Liquidation of
partners risk
Risks of liquidating
the subcontractor’s
business or the failure
of such subcontractor
to fulfil its contractual
obligations.
These risks may arise in
phases of construction
and/ or operation.
The main partners working in the
project under subcontracts must
have necessary skills, knowledge
and experiences to fulfil the con
tractual obligations regarding the
desired performance level.
project under subcontracts must
have necessary skills, knowledge
and experiences to fulfil the con
tractual obligations regarding the
desired performance level.
Obtaining prior consent of the
Federal Entity with regard to sub
contracting with alternative main
partners.
The responsible Federal Entity
shall perform due diligence by
conducting extensive studies
that include reviewing the data
of first-class subcontracting part
ners to make sure that they can
overcome risks they encounter.
The Private Partner
Tax Risks
Changing the applied
tax fees (for example,
income tax or value
added take “VAT”) or
imposing new taxes
may result in reducing
the expected revenues
from the rights of con
tribution in the project.
If changes result from unexpect
ed discriminatory acts or behav
iors, a special compensation shall
be granted to the Private Partner
Public Sector Entity
Technical Risks
The following may
occur:
1- The technical
inputs of the activities
assigned by the
governmental authority
to external contractors
may fail to provide
inputs that comply
with the required
specifications.
2- The technical inputs
may not cope with the
modern updates and
advances in the field of
technology
The private partner must,
from time to time, update the
technologies used in the project
to keep pace with advances and
to fulfil the project specifications
and requirements.
Apply penalties in case of
the failure to comply with the
specification of project outputs
to keep pace with advances and
to fulfil the project specifications
and requirements.
Apply penalties in case of
the failure to comply with the
specification of project outputs
The Private Sector
Partner
84
Manual on PPP projects, management and execution
STAGE
ACTION
1. Procurement stage of
the PPP project
lifecycle
The project team provides a support role to the
Concerned Entity in developing the KPIs
2. Tendering
The performance requirements are identified and
defined. Later, the area-specific KPIs are developed
and detailed
3. Contract Management
KPIs are measured and monitored to assess wheth
er the private partner is meeting the standards
agreed upon in the contract
KPI Types
TYPE
EXAMPLE
Service Quality
Road Project: Quality of road
Water Supply: Project continuous water supply,
supply of treated water not as per prescribed
quality
Financial Efficiency
Average cost of ambulance trip
Process Related
Airport Project: Arrival processing time at airport,
average connection time
Water Project: Delay in recording meter readings
and entry in computerized billing system
Key Performance Indicators (KPIs)
KPIs are the methods used to evalu
ate the performance of a particular
project. These evaluations typically
compare the actual and estimated
performance in terms of effective
ness, efficiency, and quality. They are
determined from the technical and
economic studies.
KPI Development Process
ANNEX 6
KPIS
> Appendix
KPIs can be both qualitative and
the influence of economic, le
gal, political environment in a
particular host country of the
projects
All indicators should be dynamic and measurable to reflect the
efficiency, customer satisfaction, business success, product re
quirement, and future potential of the projects. Any performance
change can also be measured by these indicators.
Physical Characteristics of
Project
Financing and Marketing Indicators
Process Indicators
> Appendix
86
Manual on PPP projects, management and execution
> Appendix
1. PROJECT
CHARACTERISTICS
2. PROJECT FINANCIAL AND
MARKETING INDICATORS
3. PROJECT PROCESS
— Type of building
— Level of design complexity
— Level of construction
complexity
— Level of technologically
advancement
Concessionaire’s knowledge
of PPP Government’s
knowledge of PPP
— Competitive tender
procedure
— Standard PPP contract with
enough flexibility General
public/social support
— Stable and favorable macro-
economic condition
— Stable and favorable
environment
— Stable and favorable
political environment
— Commitment and
responsibility between
public and private sectors
— Project technical feasibility,
constructability, and
maintainability
— Appropriate risk allocation,
sharing and transfer
— Sound financial analysis
— Sustainable profitability
— Increased marketability
— Financial ability of whole
shareholders
— Financing cost
— Perfect tariff/tolls or price
adjustment mechanism for the
project
— Realistic schedule of investment
and revenue
— Financial ability of whole
shareholders
— Financing cost
— Perfect tariff/tolls or price
adjustment mechanism for the
project
— Realistic schedule of investment
and revenue
— Insurance cover
— Construction and concession
period
— High quality controls
— Safety management
— Health control
— Environment protection
— Effective risk management
system
— Facility management
— Stress/conflicts
management
— Resource utilization
(material and equipment)
— Contract management
— Prominent technical
management and skill
— Interface management
between organizations and
stages
— Time management
— Cost management
— Good governance
— Innovation and Learning
Indicators
— Investment in research
and development of new
technology
— Establishment of learning
organization
— Employee Training
— Technology innovation (e.g.
designing, construction,
planning, etc.)
— Technology transfer
— Financial innovation (e.g.
creative financial package)
— Stakeholder Indicators
— Public client’s satisfaction
— General public/Social
satisfaction
— Good relationship among the
concessionaire, subcontractors,
and suppliers
— Good relationship in project
team
87
Manual on PPP projects, management and execution
FORM
TIME
COST
BINDING
Negotiation
Varies
Low
No
Mediation
Fast
Low
Not unless agreed to
Arbitration
Slow
High
Yes
Expert Determination
Fast
Moderate
Not unless agreed to
Litigation
Slow
High
Yes
> Appendix
ANNEX 7
CONFLICT RESOLUTION SUMMARY
88
ence to national standards.
Default and Remediation Procedures:
Clear procedures should be outlined in
case of default by the private partner,
including steps for remediation and
the rights of financing entities in such
events.
Right of First Refusal:
The Federal Entity should retain a right
of first refusal in cases of significant
changes in project ownership or control,
to safeguard public interest.
ANNEX 9
MORTGAGES ON ASSETS AND RIGHTS
OF THE FINANCING ENTITY
93
Manual on PPP projects, management and execution
93
Manual on PPP projects, management and execution